Commissioning and Installation Instructions
5.1
Before Installation
The individual performing the installation must have access to the commissioning tools provided by
the Energy Services Company (ESCo).
An SS9002 ESBox or other compatible ZigBee network coordinator device must be present at the
site, and be authorised to communicate with a control server provided by the ESCo.
The radio environment at the location of installation may be tested to ensure the new device will be
able to connect to the existing ZigBee network. For more information on radio environment test
equipment and procedures, please contact Saturn South.
There are two stages to device installation:
1.
Installation
- Identify the circuit in which the device will be used, confirm that there is
sufficient space to mount the device.
2.
Commissioning
- Wire the device into the switchboard as per the guidelines below and apply
power.
5.2
Installation
The SS9007 Mini CT Meter is designed to be straightforward to install into a standard domestic or
commercial switchboard.
The SS9007 Mini CT Meter requires a phase and neutral connection to the device, both to power the
device and to provide a reference for high accuracy voltage measurements. The reference phase
connected to the device must be the same phase from which the load current is to be sensed by the
supplied clip-on Current Transformer, and must be drawn downstream from an existing or dedicated
protection device (e.g. MCB or RCD).
The following steps should be followed to install the device:
1.
Identify the circuit that is to be monitored by the device. Note the major appliance or load
that the circuit is connected to for future reference, and if necessary make a note of the
device's HAN address.
2.
Ensure that there is adequate mounting space for the device within the switchboard.