Commissioning and Installation Instructions 

5.1

 

Before Installation 

The individual performing the installation must have access to the commissioning tools provided by 
the Energy Services Company (ESCo). 

An SS9002 ESBox or other compatible ZigBee network coordinator device must be present at the 
site, and be authorised to communicate with a control server provided by the ESCo. 

The radio environment at the location of installation may be tested to ensure the new device will be 
able to connect to the existing ZigBee network. For more information on radio environment test 
equipment and procedures, please contact Saturn South. 

 

There are two stages to device installation: 

1.

 

Installation

 - Identify the circuit in which the device will be used, confirm that there is 

sufficient space to mount the device. 

2.

 

Commissioning

 - Wire the device into the switchboard as per the guidelines below and apply 

power. 

 

5.2

 

Installation 

The SS9007 Mini CT Meter is designed to be straightforward to install into a standard domestic or 
commercial switchboard. 

The following steps should be followed to install the device: 

1.

 

Identify the circuit that is to be monitored by the device. Note the major appliance or load 
that the circuit is connected to for future reference, and if necessary make a note of the 
device's HAN address. 

2.

 

Ensure that there is adequate mounting space for the device within the switchboard. 

The SS9007 Mini CT Meter requires a phase and neutral connection to the device, both to power the 
device and to provide a reference for high accuracy voltage measurements. The reference phase 
connected to the device must be the same phase from which the load current is to be sensed by the 
supplied clip-on Current Transformer, and must be drawn downstream from an existing or dedicated 
protection device (e.g. MCB or RCD). 

 

 

 

Содержание SS9007.2 Mini

Страница 1: ...D401 2 5 30 Dec 2015 SS9007 2 Mini CT Meter User Manual Version 5 Std HA Release build 5977...

Страница 2: ...Specifications 6 5 Commissioning and Installation Instructions 7 5 1 Before Installation 7 5 2 Installation 7 5 3 Commissioning 11 6 Switching 12 7 Metering 13 8 Device Clusters and Attributes 14 8 1...

Страница 3: ...ent failure This product is not intended for use by persons including children with reduced physical sensory or mental capabilities or lack of experience or knowledge unless they have been given super...

Страница 4: ...ill join any ZigBee HA network with Permit Joining mode enabled When the button is pressed the button colour will change to yellow and then begin to rapidly blink green once is has been held long enou...

Страница 5: ...ss 1 with a customizable reporting frequency of up to 1Hz Import export energy accumulations and true signed power measurements make the SS9007 an ideal choice for monitoring renewable generation sour...

Страница 6: ...Range 25 C to 80 C Relative Humidity 10 95 non condensing Average Power Consumption 1W Mass 0 080kg Dimensions 60 5 x 90 x 17 5mm Wire gauge 0 1mm2 min 2 5mm2 stranded or 2 5mm2 solid core max IP Rati...

Страница 7: ...Commissioning Wire the device into the switchboard as per the guidelines below and apply power 5 2 Installation The SS9007 Mini CT Meter is designed to be straightforward to install into a standard do...

Страница 8: ...terminals 5 Clip the CT on to the target load conductor ensuring that the arrow on the CT points towards the load or generator away from the grid Connect the output of a MCB RCD or other protection de...

Страница 9: ...connected in the correct polarity to ensure proper operation The Live terminal Neutral terminal two Current Transformer CT terminals CT BLACK and CT WHITE and two SWITCH terminals are marked on the s...

Страница 10: ...monitoring 7 If your Mini CT Meter has switching capability the two terminals marked SWITCH are connected internally to an isolated relay rated for 5A at 240V The front panel button will glow amber t...

Страница 11: ...econd window devices may be joined to the network by repeating step 2 If this site is being commissioned for the first time it is recommended that a factory reset be performed on the ESBox before acti...

Страница 12: ...to a digital IO on a control device such as a PLC The example below shows a SS9007 Mini CT Meter being used to control an external contactor with a 240V coil by switching the active input to the conta...

Страница 13: ...plied CT IMPORTANT Attaching a third party CT to the device can damage the device and will void the product warranty SS9007 Mini CT Meter devices have a variant label on the front panel that describes...

Страница 14: ...not be possible for a device to send 11 attributes in a single report If the total size of the report exceeds the maximum payload size 60 bytes some attributes will be excluded from the report The de...

Страница 15: ...the Simple Metering Cluster on endpoint 10 0x0A Attr ID Attr ID Hex Attribute Name Units Divisor Writeable 57610 e10a Voltage 1 RMS Mean V 100 N 57628 e11c Current 1 RMS Mean A 100 N 57646 e12e Power...

Страница 16: ...mit Joining mode Try to join the device again Saturn South metering devices will initially scan a reduced subset of the full range of available ZigBee channels If the network is on a channel that is n...

Отзывы: