background image

Adhesive insulation tape

Insulating the pipe

Insulating  

header joint

Insulating after brazing the cap

Adhesive insulation tape

Insulator

Header joint

 

Cover the connected part and fasten the header joint using a cable tie.

 

Insulate the header joint and the brazed part and wrap the connected 

part with an adhesive insulation tape to prevent it from dewing.

Installing the Header joint

1. Select the reducer fitted on the diameter of the pipe. 

Reducer

Pipe

To indoor unit

Pipe

<Liquid side>

To outdoor unit

Brazed part

Provided

Reducer

Pipe

To indoor unit

Pipe

<Gas side>

To outdoor unit

Note 

 Connect the Outdoor joint to the pipe by cutting the outlet of the Outdoor joint or provided reducer properly.

10~15mm or more

±10°  

or less

The  

horizon

Reducer Header joint

Pipe

3. Install the header joint horizontally.

±15° 

or less

The horizon

±10° 

or less

The horizon

<Liquid side>

±15° 

or less

The  

horizon

The horizon

<Gas side>

The horizon

Installation of outdoor joints

Do not install the outdoor 

joint in this direction.

Liquid pipe

High pressure 

gas pipe

Gas pipe

Connecting Method

Installing the Y-joint 

Insulating the branch joint

Y-joint & liquid side & gas side of the outdoor unit

 Attach the insulation provided with a branch joint to the insulation supplied in the field  

without a gap. Wrap the connected part with an insulation (Field supply) of a thickness of at 

least 10mm.

 Use an insulation with the heat resisting temperature over 120°C.  

Wrap the branch joint with an insulation of a thickness of at least 10mm.

 When insulating in high humidity(higher than 30°C, 80%), wrap the supplied insulation with 

more than 10mm of extra insulation such as Polyethylene Foam or other similar material.

 Wrap the connected part between the Outdoor joint and the gas side of the outdoor unit to 

prevent it from defrosting. Wrap gas side pipe of the outdoor unit wholly to prevent it from 

dewing.

 

 

 Attach the adhesive insulation tape to the pipe 

as shown in the picture after insulating the pipe.

Insulation tape 

(Field supply)

Pipe insulation  

(Field supply)

Pipe

Fix securely without any gap.

Pipe insulation 

Provided

Fix securely  

without any gap.

Pipe insulation  

(Field supply)

Pipe insulation  

(Field supply)

150mm

Branch 

joint

A thickness of the insulation (Field supply) 

should be at least 10mm.

(Field supply)

2.  Block the reducer that is not used by brazing the cap if the number of connected indoor 

unit is fewer than header joint holes.

Blocked the hole of  

header joint

In order

<Gas side>

<Liquid side>

Blocked the hole of  

header joint

In order

Provided

Brazed part

Note 

Connect the header joint to the pipe by cutting the provided reducer properly.

10~15mm

or more

  Connect the header joint in order respecting the number of the indoor unit.

  Connet the indoor unit as the highest capacity comes first.

<Install vertically>

<Using reducer>

-  Use connection part of Y-joint or provided 

reducer by cutting them in accordance with 

diameter of connecting pipe.

-  Make certain 10~15mm or more for reducer 

which connected with pipe.

-  Remove burr on cut part of reducer.  

It is impossible to connect reducer with pipe,  

if pipe is deformed or reducer is untrimmed.

10~15mm

or more

  Keep a minimum distance of 500mm or more before 

connecting a branch joint.

<Install horizontally>

Maintain ±15° on  
the horizon

 

  Install the Y-joint within ±15° on  
the horizon or on the vertical.

500mm  
or more

Main pipe

To outdoor unit

Pipe

Front  

Rear

Rear

Pipe

Reducer

To other branch 

joints or indoor unit

Reducer

  Do not insert the pipe deeply into the Y-joint. 

( Do not insert more than 70mm.)

<Insertion depth of the connecting pipe>

Connecting pipe

Connecting pipe

 

 Basic specification

 

  When cutting the connection part

<Gas side>

 

 

 Use the attached reducer according to the selected pipe size.

Pipe

Reducer

Reducer

Pipe

To other outdoor unit

To other outdoor joint or Y-joint of the main pipe

To other outdoor joint or outdoor unit

Install the Y-joint ‘horizontally’ or ‘vertically’.

Installing the Outdoor joint

<Liquid side>

 

 

 Use the attached reducer according to the selected pipe size.

Pipe

Reducer

Pipe

To other outdoor unit

To other outdoor joint or Y-joint of the main pipe

To other outdoor joint or outdoor unit

 

 

 Use the attached reducer according to the selected pipe size.

Pipe

Reducer

Reducer

Pipe

To other outdoor unit

To other outdoor joint or Y-joint of the main pipe

<High pressure gas side>

To other outdoor joint or outdoor unit

 

 

 High pressure gas pipe only applies to the HR product.

Reducer

DVM OPTION-MXJ_IM_03340A-05_EN.indd   2

2015-06-12   오후 4:06:26

Отзывы: