Unit: mm
Outdoor unit
Anchor bolt
Nut, Spring wahser
H-beam
Square pad
A+10~20mm or more
A
20mm
75mm or
more
Base construction and installation of the outdoor unit
1 . Install the outdoor unit 150mm higher than the base ground and install the drain hole to connect the pipe to the
drainage .
2 . When the front fan of an outdoor unit is installed in a place where the average snowfall is more than 150mm, the
discharge duct should be attached to the outdoor unit .
3 . The concrete foundation should be 1 .5 times larger than bottom of the outdoor unit .
4 . It is necessary to install wire mesh or steel bar when outdoor units are installed on a soft foundation .
5 . When installing multiple outdoor units at the same place, install the H beam on the base ground . (When installing a
number of outdoor units, you can install it on the base ground .)
6 . Install the H beam(150mm x 150mm x t10 : basic specification) or vibration absorption frame to jut out from the base
ground .
7 . After installing the H beam, apply corrosion protection .
8 . Install a square pad(t=20mm or more) to prevent vibration from the outdoor unit onto the base ground . Place the
outdoor unit on the H beam and fix it with the bolt, nut and washer . (Fix with M10 basic anchor bolt, nut and washer .)
Installation of outdoor unit
•
Make sure to remove the wooden pallet before installing the outdoor unit . If you do not remove the wooden pallet,
there is risk of fire during welding the pipes .
•
If the outdoor unit is installed with wooden pallet on, and it was used for long period time, wooden palette may break