5.3 

MONTHLY INSPECTION 

 

 
 

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *  

 

ONLY CARRY OUT WHEN INSTALLATION IS COOL AND AT A STANDSTILL 

 

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

 

 

This  check  may  only  be  carried  out  by  skilled  mechanics.  Observe  the  safety  very 
carefully, the enclosure must be removed and rotating parts will be accessible.  

 
A: 

Lubricate cross journals of the PTO-shaft (after approx. 40 operating hours)  

 

 

B: 

Lubricate latches and padlock and check their functioning.  

 
C: 

Preserve the compressor w hen it has been at a standstill for a longer period of time.   

 

(lubricate the compressor’s rotor w ith oil to prevent corrosion) 

 

To  carry  out  the  follow ing  inspections  it  is  necessary  to  start  the  installation 
w ithout enclosure. Please note the dangers that can occur as a result of access to: 

 

- hot parts as compressor and silencer (150 ° C) 

 

- rotating parts such as the transmission and the fan 

 

- high sound levels (>  85 dB) 

 

HEARING PROTECTION OBLIGATED!! 
 
DURING INSPECTION NO ONE IS ALLOWED UNDERNEATH THE VEHICLE!! 

 
D: 

Check the functioning of the safety valve. 
Air pressure measured at the discharge flange of the compressor may not exceed a 
maximum gauge pressure of 2.5. 

 

Potential pressure loss betw een compressor and silo tank of 0.2 up to 0.3 bar  

 
E: 

Check  flanges/packing,  rubber  compensators  etc.  in  the  enclosure  for  air  leakages 
to avoid loosening of the insulation material and overheating. 

 
F: 

Check the functioning of the fan. 

 
U: 

If  the  installation  is  equipped w ith  an external  oil-cooler  check  if the  control  light  is 
on (image 3.1.2). You w ill find the safety f use in the sw itch box. 

 
 
 
           
 

 

 

 

 

Содержание GHH CS750

Страница 1: ...INSTRUCTION AND OPERATING MANUAL Compressor installation CS750 direct driven ...

Страница 2: ...0 544 377050 The manual provides information about the following installation GHH CS750 direct DRIVEN Carefully read these instructions and the compressor instruction before setting up and going into operation These manuals contain essential information that must be read to ensure interference free operation and to achieve longevity Repairs maintenance or conversion work shall only be carried out ...

Страница 3: ...on and training personnel 6 2 3 Operating safety conscious 6 2 4 Safety instructions operator 6 2 5 Modifications and repairing spare parts 6 2 6 Modifications installation 6 3 Mounting installation 7 3 1 Mounting instructions RTI installation direct driven 7 4 Start up 8 5 Maintenance installation 9 5 1 Inspection during operation 9 5 2 Weekly inspection 10 5 3 Monthly inspection 11 5 4 Half year...

Страница 4: ...n the PO number when contacting us by phone or mail You will find the PO number on the type plate of the installation Telephone number 0031 544 377050 Fax 0031 544 376499 Email info rti nl 1 2 Service facilities For addresses of service technical support facilities please visit our website www rti nl 1 3 Technical data compressor ...

Страница 5: ...o be used The respective viscosity class SAE class can be taken from the following diagram Image 1 3 3 1 4 Oil cooler A GHH CS750 is equipped with an integrated oil cooler If this oil cooler is removed to save space the installation is equipped with an external oil cooler An external oil cooler is equipped with a 24 volt fan The fan must be rotating during operation and therefor the functioning of...

Страница 6: ...nts The latest edition of each of these regulations shall be applicable Any special official codes and regulations particularly safety regulations applicable to your operation in view of the local conditions shall be observed likewise In the event of competing regulations the most severe requirements shall apply 2 4 Safety instructions operator Securing the compressor s operational safety is the r...

Страница 7: ...asure the PTO shaft Make sure the installation doesn t exceed the width of the truck D Measure the brackets and try to use all the holes in the chassis Brackets should be painted or otherwise protected against corrosion With a box or tank combination at least 4 brackets should be used E Mount the brackets onto the chassis and onto the installation F If the installation is equipped with an external...

Страница 8: ...ll also start to run and will ensure the supply of oil to lubricate the bearings and the gears The oil pressure shall not fall below 0 3 bar With cold oil it may occur that the required oil pressure is built up only after a short operating time due to higher viscosity Check the air indicator clock When red the compressor must be switched off See inspection checklist The minimum engine speed cannot...

Страница 9: ... C The safety valve must open at maximum air pressure This valve must NOT be used as blow off valve To prevent overheating in the enclosure the valve at the silo tank must blow off before the compressor valve does blow off pressure 2 5 bar D Pay attention to any unusual sounds or peculiarities near the installation E The fan must rotate to a switched on PTO Check the functioning of the fan This ch...

Страница 10: ...filter is reinserted in the same position paying attention to the front and back of the element Image 5 2 1 Also check the functioning of the air indicator C It is important to check the airflow and cleanliness of the fan louvres to prevent overheating of the compressor compressed air cooler and when installed the oil cooler D Check the functioning of the fan This check may only be carried out by ...

Страница 11: ...art the installation without enclosure Please note the dangers that can occur as a result of access to hot parts as compressor and silencer 150 C rotating parts such as the transmission and the fan high sound levels 85 dB HEARING PROTECTION OBLIGATED DURING INSPECTION NO ONE IS ALLOWED UNDERNEATH THE VEHICLE D Check the functioning of the safety valve Air pressure measured at the discharge flange ...

Страница 12: ...t the non return valve installed in the discharge silencer and check for proper functioning D Check the functioning of both fans E Check if the control light is on You will find the safety fuse in the switch box F Check the shear pin coupling for leeway space NOTE The operating instructions provided by the compressor manufacturer should be read carefully 5 5 Maintenance inspection list Along with ...

Страница 13: ...ter element ENCLOSURE O Check the insulation material in the enclosure for damages cover back panel floor panel if necessary repair and finish with sealant O Check if the fan louvers are open O Check if the discharge silencer is clean flow O Check the frame and brackets for potential cracks O Check if the bolts of the brackets are secured O Check the seal washers of the Storz coupling for cracks a...

Отзывы: