background image

Installation Instructions 
Roxtec B frame

For correct casting of frames 
into concrete walls, casting 
moulds in cellular plastic are 
available.

Frame Assembly

Remove the protective foil from the 
sealing strip on every short side.

Assemble the frame by inserting the bolts and tighten the nuts. The frame 
can easily be assembled around already routed cables or pipes. 

Installation, Casting

Before concrete is poured, 
the frame and casting mould 
is fixed in position with the 
frame flange inside the wall.

To be able to make a correct 
installation the size of the 
opening in the wall must be 5 mm 
(0.197") wider than the inside 
dimensions of the frame on all 
sides. The reason for this is the 
fact that the stayplates need this 
space to be able to move inside 
the frame during installation and 
compression.

The B frame cast and sealed in 
concrete wall.

Содержание B frame

Страница 1: ...mbled around already routed cables or pipes Installation Casting Before concrete is poured the frame and casting mould is fixed in position with the frame flange inside the wall To be able to make a correct installation the size of the opening in the wall must be 5 mm 0 197 wider than the inside dimensions of the frame on all sides The reason for this is the fact that the stayplates need this spac...

Страница 2: ...4 x5 Frame mm in mm in B frame aperture dimensions for bolted installations Theoretically recommended dimensions Mark a rectangular opening according to frame type see table below Use the frame as template for the drilling of the screw holes Hole in flange Ø 9 mm 0 354 Attach the frame to the cabinet wall using bolts and nuts An optional rubber gasket can be placed between frame and cabinet wall T...

Страница 3: ... the finished row of modules Before inserting the final row of modules insert two stayplates Separate the two stayplates and insert the final row of modules between the stayplates Drop the upper stayplate on top of the modules Lubricate all sides of the wedge sparsely except front and back Please read the markings on the wedge and turn it correctly before inserting it in the top of the frame stand...

Страница 4: ...ore exposing the cables pipes to strain or pressure To be used with RM components To simplify installation in combination frames fill all openings before tightening the wedge Cables shall go straight through the frame Packing space Frame sizes 2 4 6 and 8 accommodate the following height of modules 60 mm 120 mm 180 mm and 240 mm As example shows for frame size 6 the 180 mm can be the result of 4 r...

Отзывы: