5. 

Commissioning 

Preparations 

 

 

Attention

 

Make sure that the machine frame (rack, substructure, etc.) is connected to the protective earth conductor 
(PE). Protective earthing has to be provided by user as necessary. 

 

 

Attention

 

It is imperative that the vibrating motor be connected to the equipotential bonding system of the overall equipment be-
fore commissioning. 
 The adaptation points are marked with earth symbols. 
See also: DIN EU 60204 / VDE 0100-540

 

 

 

Attention

 

Electrical connection of the vibratory feeder must be made by trained professional electricians only! When 
making any change to the electrical connection make absolutely sure that the 'Control Units' operating in-
structions are duly observed. 

 
Verify that 

  the vibratory feeder is arranged freely without contact to any solid body. 

  the bowl is firmly bolted in place 

  the vibratory feeder connecting cable is plugged into the control unit. 

  The available electricity supply (frequency, voltage, power) must correspond to the connection data of the con-

trol system (see rating plate on the control unit). 
 

Plug the cable of the control unit into a power socket and operate the power switch to energize the control unit. 
 

 

Notice

 

For vibratory feeders that are supplied as a completely set-up system the optimum feed rate has been fac-
tory-set.  It  is  marked  with  a  red  arrow  on  the  dial  of  the  rotary  knob. In  this  case  set  the  rotary  knob  (or 
keys) to this mark. 

 
Optimum  tuning  is  achieved  when  the  desired  feeder  speed  is  obtained  with  a  controller  setting  of  80  %.  In case  of 
larger deviations (> +/- 15%) you should re-tune the system. 
 

Tuning 

 
Vibratory feeders are factory-tuned for standard feeder bowls (without orienting devices). 
To  ensure  optimum  sorting  behaviour  the  vibratory  feeder  has  to  be  fine-tuned  for  the  actual  local  operating  condi-
tions. 
 
Tuning is done by adding or removing leaf springs and spacers. 
First check that the correct control unit is connected (see table with frequency, voltage and power ratings in Section 1). 
Now perform following steps: 
 

  Unscrew  the  sheet  metal  enclosure.  Firmly  tighten  all  spring  and  bowl  fastening  screws.  For  the  tightening 

torque of spring fastening screws refer to section 1 'Technical data'. 

  Check that the magnets are compatible with the voltage and frequency ratings specified under Technical Data. 

  Measure the air gap. Adjust the air gap to the correct setting if it doesn't match the values specified under Tech-

nical Data. 

  Fill the bowl with parts. Switch the vibratory feeder on and set the feeding capacity to 90% via the rotary knob 

(or keys). 

  Loosen the bottom fastening screw on one spring pack (by about a quarter turn or half turn). 

 

 

Содержание SRC-B 200-2

Страница 1: ...Installation and Operating Instructions Vibratory Feeders SRC N 160 2 SRC N 200 2 SRC B 200 2 SRC N 250 2 SRC B 250 2 SRC N 400 1 SRC N 400 2 SRC N 630 1 SRC N 800 1 SRHL 400 1 SRHL 400 2...

Страница 2: ...data 4 2 Safety directives 7 2 1 Applicable directives and standards 8 3 Design and functional description 8 4 Shipment and installation 10 5 Commissioning 12 5 1 Feeder speed decreases 13 5 2 Feeder...

Страница 3: ...ow Voltage Directive 2014 35 EU We hereby declare that the product meets the following requirements Low Voltage Directive 2014 35 EC Applied harmonised standards DIN EN 60204 T1 Remarks We assume that...

Страница 4: ...5000714 WZUW 080 35000721 WZUW 080 35000721 WZAW 060 35000727 WZAW 060 35000727 YZAW 080 35000739 Magnet colour black black black black black red Air gap mm 0 3 0 5 0 4 0 5 0 4 0 5 1 1 2 1 1 2 2 3 2 8...

Страница 5: ...5 0 5 0 5 1 4 Power input2 VA 786 1140 1060 1000 1700 Current 2 A 4 05 5 7 5 3 5 8 5 Nominal magnet voltage 2 frequency 220V 50Hz Number of magnets 3 2 2 4 4 Magnet type Article number WZAW 080 350007...

Страница 6: ...Rhein Nadel Automation GmbH 6 VT MA SRC 160 800 EN_2019 20 03 2019 SJ Pin assignment With jumper The jumper must be inserted between connections 3 4...

Страница 7: ...ludes observance of the operating instructions and compliance with the maintenance rules For the technical data for your vibratory feeder please refer to the table Technical Data Section 1 Make sure t...

Страница 8: ...enting parts The driving force is provided by an electromagnetic coil The figure below is a schematic representation of a vibratory feeder Driving magnet D is rigidly connected to counter mass F When...

Страница 9: ...200 SRC N 250 SRC B 250 SRC N 400 SRHL 400 SRC N 630 SRC N 800 The controller has a 5 pin connector on its front panel for connection to the vibratory feeder Connector pin assignment is shown in the...

Страница 10: ...plastic cap and domed nut M16 Attention Do not sling or handle the vibratory feeder at or on the orienting device Take care that the vibratory feeder cannot collide with other objects during handling...

Страница 11: ...20 3 x 120 M 8 SRC B 250 220 3 x 120 M 8 SRC N 400 1 350 3 x 120 M 10 SRC N 400 2 350 3 x 120 M 10 SRHL 400 1 350 3 x 120 M 10 SRHL 400 2 350 3 x 120 M 10 SRC N 630 1 560 3 x 120 M 10 Table Drilling d...

Страница 12: ...r vibratory feeders that are supplied as a completely set up system the optimum feed rate has been fac tory set It is marked with a red arrow on the dial of the rotary knob In this case set the rotary...

Страница 13: ...0 5 2 Feeder speed increases Remove springs Start by removing one spring including spacers from one spring pack If the feeder speed continues to increase after you loosen a fastening screw anew remove...

Страница 14: ...missible sound insulating hoods can be installed which we can offer on request see our catalogue 6 Maintenance Vibratory feeders basically require no maintenance They should only be cleaned when soile...

Страница 15: ...ctor there is a risk of damage to the controller and magnet Set controller to 80 Check that coding in plug connector of the controller is correct see rating plate and Technical Data Section 1 The vibr...

Страница 16: ...uk com www rnaautomation com Manufacturing and Sales HSH Handling Systems AG Wangenstr 96 CH 3360 Herzogenbuchsee Switzerland Phone 41 0 62 956 10 00 Fax 41 0 62 956 10 10 E mail info handling systems...

Отзывы: