If your shed has an OPTIONAL TIMBER FLOOR KIT, fit this now.

•  Take all 5 x 4000mm Floor Joists and place them parallel (with 

  the narrow side of the joist on the ground) as per the diagram. 

  The outside joists are 2000mm apart and the centre 3 joists are 

  500mm spaces (to the centres).

•  Select 2 x 2000mm floorboards and lay them on the top of 

  the joists, one at each end as per the diagram. Nail the 

  floorboards to the joists, flush at the corners, with 2 x 50mm 

  clouts at each end. 

 

When completed, Measure 

diagonally

 from one outside corner 

  to the other, note the measurement and then measure the opposite 

  diagonal distance. These measurements must be the same for the 

  shed to be square. Adjust if necessary.

•  Once the shed is square, check that the spacings of the remaining 3 x joists 

are 500mm apart to the centres and nail 2 x 50mm clouts through the end 

floorboards into each joist at each end.

•  Check for square again nail another floor board at each end with 2 x nails into 

each joist.

Fig. 1

Fig. 2

Fig. 3

FLOORING - TIMBER FLOOR KIT

End Floor Boards

Joists

2000mm

500mm

500mm

500mm

500mm

FITTING THE REMAINING FLOORBOARDS

•  Next lay all of the floorboards onto the joists. Note, you may

 

need to cut down a floorboard 

lengthwise to fill the final gap 

(fig. 1). 

•  Starting from one end, lay the floorboards in place until you reach the middle of the floor. 

Then start fitting them from the other end until you have a gap near the middle of the floor 

that the last floor board won’t fit into. If you don’t need to cut one down, move to the final 

step on this page.

•  When all of the floorboards are in place, measure the width of the remaining gap and add 

3-4mm to ensure a tight fit. Cut the board lengthwise to this measurement (fig. 1).

•  Remove 2 full floorboards and fit the cut down board (fig.2). Make sure that the ends of all 

the boards are straight and aligned with the joists at both ends.

•  Place the final 2 boards in place inverted as per fig.3, and align the ends to the rest for 

the floor. Stand firmly on the inverted boards to push them into place and tighten all of the 

floorboards.

•  Finally, nail all of the floor boards to the joists with 2 x nails per board into each joist.

Your floor is now complete and ready for your shed!

(Note: Images not drawn to scale)

 

Содержание Duratuf TAMAHERE

Страница 1: ...ASSEMBLY INSTRUCTIONS TAMAHERE BASE SIZE 4 000m x 2 000m...

Страница 2: ...of sharp edges on steel cladding and flashings Protect your eyes and ears Use electric power tools with care Use a Safety Trip Switch It is easier and quicker if this shed is assembled by two people...

Страница 3: ...llow 2 295m 11 Stud 70 x 45 H1 Yellow 0 320m 5 Stud 70 x 45 H1 Yellow 1 930m 2 Top Plate Packer 70 x 45 H1 4 000m 1 Centre Ridge Beam 140 x 45 H1 4 000m 1 Nog 70 x 45 H1 0 908m 4 Nog 70 x 45 H1 0 665m...

Страница 4: ...Downpipe Cover Flashing 2 260m 1 1008 Front Roof Flashing 4 115m 1 1009 Front Top Plate Flashing 4 000m 1 1010 Spouting End Cap 0 040m 2 1011 4 HARDWARE ACCESSORIES DESCRIPTION LENGTH QTY DIAGRAM CHEC...

Страница 5: ...ted 2 000 x 0 400m 1 Joists 70 x 45mm H4 3 910m 5 Joists 70 x 45mm H4 2 000m 2 Joists 70 x 45mm H4 0 444m 12 Aluminium Door Step Flashing 2 395m 1 Floor Screws 75mm 75 Floor Screws 40mm 75 Tek Screws...

Страница 6: ...e centre of the front and measure 1200mm each way This is the position of the 2400mm door and where you will slope the concrete for water runoff When you have poured your concrete starting from 100mm...

Страница 7: ...e 4000mm base plate Green one 4000mm top plate Red and six studs Yellow Lay out the framing on a flat surface as per the diagram with the top plate at the top Ensure that the notches on the top and bo...

Страница 8: ...nd nail them in place using 2 x 75mm nails top and bottom Now position the 2 x 1930mm Lintel Support Studs to the inside of the door studs and down against the base plate Secure with 2 x 75mm nails at...

Страница 9: ...upright framing plates While someone supports the frame to ensure that it doesn t move around nail this back frame in place with 2 x 75mm nails at each corner Carefully roll the frame over onto its ba...

Страница 10: ...il to the top plate using 75mm nails 1 at each end and 4 evenly spaced Take the centre Roof Beam and position over the 2 end wall studs and attach using 2 x 75mm nails at each end Select the Roof Beam...

Страница 11: ...Ensure that the bottom wall frames are running straight and that the studs either side of the door are in the right place Measure diagonally from one inside corner to the other note the measurement an...

Страница 12: ...R KIT End Floor Boards Joists 2000mm 500mm 500mm 500mm 500mm FITTING THE REMAINING FLOORBOARDS Next lay all of the floorboards onto the joists Note you may need to cut down a floorboard lengthwise to...

Страница 13: ...e corner to the other note the measurement and then meaure the opposite diagonal distance These measurements must be the same for the shed to be square Adjust if necessary 13 Place one sheet of plywoo...

Страница 14: ...t 600mm apart See the blue highlights in the diagrams below Wrap the tape around the corner and nail it in the same position to the other 3 sides of the shed CORNERS AND DOOR STUDS On the front corner...

Страница 15: ...her I Select the door head flashing and hold it up underneath the lintel It should fit snugly between the door studs Holding the flashing in tight nail it to the lintel using 6 x 30mm clouts 3 x on th...

Страница 16: ...ings between two sheets Remove all metal filings before riveting Carbon in pencils reacts with the Zinc Aluminium coating on steel Use an ink pen to mark the steel as required WALL CLADDING FIXING PAT...

Страница 17: ...ng Fixing Pattern on the previous page To fix the bottom of the sheet hold the top sheet flat against the framing and align the edge of the cladding and the corner stud This ensures the back wall of t...

Страница 18: ...ush with timber frame Fix with 2x 25mm Tek Screws DOOR SIDE CLADDING MIDDLE SHEET Using another 800mm door side cladding sheet lap it underneath the sheet above as per normal and place 2 x 25mm Tek sc...

Страница 19: ...rtically plumb Back at the top adjust the flashing so that it is perpendicular vertically level from the side pre drill the hole at the top parallel with the first screw and attach Repeat at the botto...

Страница 20: ...from running out Select the first end cap and dry fit it no silicone so that you are prepared and know where it will be sitting in the spouting for when you have wet silicone Pre drilling your first r...

Страница 21: ...brackets to rear wall cladding Position the downpipe cover flashing over downpipe and rivet to wall cladding using 6 rivets FITTING THE DOWNPIPE 21 FITTING THE FRONT TOP PLATE FLASHING The Front Top...

Страница 22: ...h edges of clear roof sheet overlap the steel sheets at each side vs the steel sheets that are under on one edge and over on the other Starting from one end of the shed place the first roof sheet into...

Страница 23: ...Roof flashing over the front of the corrugated roofing The front barge will also fit over the top and bottom of the side barges We are going to hold the corner together so the corner fits snug and pl...

Страница 24: ...hand side C 2 Steel locking bars D 2 SMALL PARTS BAG CONTAINING Guide clips door size dependent E 4 10 Door handle and fixing to suit F 1 Bottom rail stops and 6mm screws G 2 Faceplate and lock assemb...

Страница 25: ...sed across the opening to avoid gaps MEASUREMENTS Opening width As the standard door overlaps each side by 30mm or more the door should be 60mm wider than the 1800mm opening Opening height The door op...

Страница 26: ...with handle 80 80 HEADROOM REQUIREMENTS FOR DOORS Headroom A minimum of 410mm of headroom is required If the door is installed lower into the opening than shown below additional loss of door opening...

Страница 27: ...second bracket Re check levels then drill and fix as with first bracket PLACE DOOR ON BRACKET Do not cut plastic or packaging yet Using two persons and correct lifting techniques lift door onto the br...

Страница 28: ...h the axle forward in the slots toward the opening and tighten the nuts firmly without overtightening TENSION THE SPRINGS Ensure that the bottom rail is at the 3 o clock position as shown Ensure both...

Страница 29: ...eight as the top of the brackets B Slide four guide clips E into each guide C Position the bottom clip 200mm from the floor with the rest evenly spaced along the guide Position one guide over the edge...

Страница 30: ...line with top of locking bar Slide bars through the guide slot then back onto lock arms Screw on securely using the counter sunk screws O Ensure that locking bars do not protrude more than 20mm beyond...

Страница 31: ...Lock bar cover J WARNING Locking bar covers must be installed to prevent possible finger entrapment CLEAN UP Remove all swarf drill filings with a soft brush or rag Hose down roof and walls thoroughl...

Страница 32: ...caution b With a person at each end of the door hold the axle firmly with a large pip wrench Stillson at least 450mm long c Loosen the U bolt nuts at both ends and KEEP A FIRM GRIP ON WRENCH d Move th...

Страница 33: ...ercially available today However all exposed surfaces require some attention to guard against the premature onset of corrosion and any other harmful atmospheric effects In our atmosphere there are har...

Страница 34: ...ose the door should be about the same if door has an automatic opener put into manual mode before testing door If the door is difficult to operate in either direction up or down then check 1 that the...

Страница 35: ...ding fail to perform as specified above the liability of Riverlea Group Ltd shall in all cases be limited to replacing or repairing the defective product The balance of the original warranty will cove...

Отзывы: