17

Signal

Problem

Possible cause

Recommended remedy

2 blinks

Once the pre-purging phase 
and safety time have passed, 
the burner goes into lockout 
without the appearance of the 
flame

1

- The operation solenoid lets little gas through  . . . . . . . . 

Increase

2

- One of the two solenoid valves does not open. . . . . . . . 

Replace

3

- Gas pressure too low . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Increase pressure at governor

4

- Ignition electrode incorrectly adjusted . . . . . . . . . . . . . . 

Adjust, see fig. (D) page 8

5

- Electrode grounded due to broken insulation  . . . . . . . . 

Replace

6

- High voltage cable defective  . . . . . . . . . . . . . . . . . . . . . 

Replace

7

- High voltage cable deformed by high temperature  . . . . 

Replace and protect

8

- Ignition transformer defective. . . . . . . . . . . . . . . . . . . . . 

Replace

9

- Incorrect valve or transformer electrical wiring  . . . . . . . 

Check

10 - Defective control box . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Replace

11 - A closed valve upline the gas train  . . . . . . . . . . . . . . . . 

Open

12 - Air in pipework . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Bleed air

13 - Gas valves unconnected or with interrupted coil . . . . . . 

Check connections or replace coil

3 blinks

The burner does not switch 
on, and the lockout appears

14 - Air pressure switch in operating position . . . . . . . . . . . . 

Adjust or replace

The burner switches on, but 
then stops in lockout

-  Air pressure switch inoperative due to insufficient air 

pressure:

15 - Air pressure switch incorrectly adjusted. . . . . . . . . . . . . 

Adjust or replace

16 - Pressure switch pressure test point pipe blocked . . . . . 

Clean

17 - Poorly adjusted head . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Adjust

18 - High pressure in the furnace . . . . . . . . . . . . . . . . . . . . . 

Connect air pressure switch to fan suction 
line

Lockout during pre-purging 
phase

19 - Defective motor control contactor  . . . . . . . . . . . . . . . . . 

(only three-phase version)

Replace

20 - Defective electrical motor. . . . . . . . . . . . . . . . . . . . . . . . 

Replace

21 - Motor lockout (defective electrical motor)  . . . . . . . . . . . 

Replace

4 pulses

The burner switches on, but 
then stops in lockout

22 - Flame simulation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Replace the control box

Lockout when burner stops

23 - Permanent flame in the combustion head or   . . . . . . . . 

flame simulation

Eliminate persistence of flame or replace 
control box

7 blinks

The burner goes into lockout 
immediately following the 
appearance of the flame

24 - The operation solenoid lets little gas through  . . . . . . . . 

Increase

25 - Ionisation probe incorrectly adjusted . . . . . . . . . . . . . . . 

Adjust, see fig. (D) page 8

26 - Insufficient ionisation (less than 5 A) . . . . . . . . . . . . . . . 

Check probe position

27 - Earth probe  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Withdraw or replace cable

28 - Burner poorly grounded . . . . . . . . . . . . . . . . . . . . . . . . . 

Check grounding

29 - Phase and neutral connections inverted . . . . . . . . . . . . 

Invert them

30 - Defective flame detection circuit  . . . . . . . . . . . . . . . . . . 

Replace the control box

Burner goes into lockout dur-
ing operation

31 - Probe or ionisation cable grounded . . . . . . . . . . . . . . . . 

Replace worn parts

10 blinks

The burner does not switch 
on, and the lockout appears

32 - Incorrect electrical wiring . . . . . . . . . . . . . . . . . . . . . . . . 

Check

The burner goes into lockout

33 - Defective control box . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Replace

34 - Presence of electromagnetic disturbances in  . . . . . . . .   

the thermostat lines

35 - Presence of electromagnetic disturbance . . . . . . . . . . . 

Filter or eliminate 

Use the radio disturbance protection kit

No blink

The burner does not start 

36 - No electrical power supply . . . . . . . . . . . . . . . . . . . . . . . 

Close all switches - Check connections

37 - A limiter or safety control device is open . . . . . . . . . . . . 

Adjust or replace

38 - Line fuse blocked . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Replace

39 - Defective control box . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Replace

40 - No gas supply  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Open the manual valves between contactor 
and train

41 - Mains gas pressure insufficient . . . . . . . . . . . . . . . . . . . 

Contact your GAS COMPANY

42 - Minimum gas pressure switch fails to close. . . . . . . . . . 

Adjust or replace

The burner continues to 
repeat the start-up cycle, 
without lockout

43 - The gas pressure in the gas mains lies very close to the 

value to which the minimum gas pressure switch has 
been set. The sudden drop in pressure after valve open-
ing causes temporary opening of the pressure switch 
itself, the valve immediately closes and the burner 
comes to a halt. Pressure increases again, the pressure 
switch closes again and the ignition cycle is repeated. 
And so on

Reduce the minimum gas pressure switch 
intervention pressure. Replace the gas filter 
cartridge.

Ignition with pulsations

44 - Poorly adjusted head . . . . . . . . . . . . . . . . . . . . . . . . . . . 

Adjust. See page 9

45 - Ignition electrode incorrectly adjusted . . . . . . . . . . . . . . 

Adjust, see fig. (D) page 8

46 - Incorrectly adjusted fan air damper: too much air . . . . . 

Adjust

47 - Output during ignition phase is too high. . . . . . . . . . . . . 

Reduce

Содержание RS 34/1 MZ

Страница 1: ...Installation use and maintenance instructions 20033803 2 08 2011 Forced draught gas burners CODE MODEL TYPE 20033785 RS 34 1 MZ 886 T 20033725 RS 44 1 MZ 873 T GB CN One stage operation...

Страница 2: ...turer cannot accept responsibility for any damage to persons animals or property due to errors in installation or in the burner adjustment or due to improper or unreasonable use or non observance of t...

Страница 3: ...essential part of the product and must not be separated from it it must therefore be kept carefully for any nec essary consultation and must accompany the burner even if it is transferred to another o...

Страница 4: ...aximum delivery 2 mbar 13 1 18 4 16 7 23 2 OPERATION On Off 1 stop min each 24 hours One stage all nothing STANDARD APPLICATIONS Boilers water steam diathermic oil AMBIENT TEMPERATURE C 0 40 COMBUSTIO...

Страница 5: ...o burn LPG GAS TRAIN ACCORDING TO EN 676 with valves pressure governor and filter see page 10 NOTE The installer is responsible for the addition of any safety device not foreseen in this manual BURNER...

Страница 6: ...burner is in lock out To reset hold the pushbutton down for between 1 and 3 seconds PACKAGING WEIGHT B approximate measurements The burner are shipped in cardboard boxes with the maximum dimensions sh...

Страница 7: ...indicates the diameter and length of the test combustion chamber Example Output 350 Mcal h diameter 50 cm length 1 5 m COMMERCIAL BOILERS The burner boiler combination does not pose any problems if t...

Страница 8: ...1 MZ Required burner output 250 kW Natural gas G 20 PCI 9 45 kWh Sm3 Pressure of the gas at an output of 250 kW from the table RS 34 1 MZ column 1 6 9 mbar Pressure in combustion chamber 2 mbar 6 9 2...

Страница 9: ...412 S2 Rp 1 1 4 MB ZR 415 S2 Rp 1 1 2 MB ZR 420 S2 Rp 2 100 0 2 2 9 2 1 150 1 6 5 6 2 8 200 3 0 9 0 4 5 3 2 250 4 9 13 2 6 5 3 3 300 6 9 18 0 8 7 4 3 3 2 350 8 9 22 9 11 2 5 4 3 4 400 10 8 28 1 14 0 6...

Страница 10: ...protective fettling must not compromise the extraction of the blast tube For boilers with a water cooled frontpiece a heat resistant cover is not necessary 7 8 C unless expressly requested from the bo...

Страница 11: ...se the application needs a particular setup it is possible to modify the central air delivery using the ring nut 4 A up to the notch indicated in diagram C In order to carry out this operation unscrew...

Страница 12: ...ted in tables C L1 The responsibility of the installer KEY TO LAY OUT FOR TABELS C C T Checking device for gas valves seal Gas train without gas valve leak detection control device device that can be...

Страница 13: ...he factory setting Before starting up the burner it is good practice to adjust the gas train so that firing takes place in conditions of maximum safety i e with gas delivery at the minimum BURNER STAR...

Страница 14: ...and then go into lockout after the safety time has elapsed Perform 10 firings with consecutive lockouts Read on the meter the quantity of gas burned This quantity must be equal to or lower than the qu...

Страница 15: ...ssure switch shown by the white mark on a blue background between the two arrows Now check the correct start up of the burner If the burner locks out again turn the knob anti clockwise a little bit mo...

Страница 16: ...rol value box starting cycle ends STEADY STATE OPERATION A At the end of the starting cycle the control box continues to check that the flame is present and that the air pressure switch is in the corr...

Страница 17: ...the exhaust gases Significant dif ferences with respect to the previous measure ments indicate the points where more care should be exercised during maintenance Gas leaks Make sure there are no gas le...

Страница 18: ...m indicated in the table on page 17 SOFTWARE DIAGNOSTICS Gives an analysis of the life of the burner through optical connections with a PC showing the working hours number and types of lockout control...

Страница 19: ...ce of the flame 24 The operation solenoid lets little gas through Increase 25 Ionisation probe incorrectly adjusted Adjust see fig D page 8 26 Insufficient ionisation less than 5 A Check probe positio...

Страница 20: ...roximately 3 seconds The number of pulses will measure the probe DETECTION TIME since the opening of gas valves according to the following table KIT INTERFACE ADAPTER RMG TO PC Code 3002719 SIGNAL FLA...

Страница 21: ...essure switch or device for checking the valve seal 3 4 pole socket for thermostat pressure switch TR 5 2 pole socket for accessories 6 6A Fittings for pipe unions Pierce if it is necessary to use the...

Страница 22: ...LED LED 3...

Страница 23: ...1 2 2 3 4 4 4 4 5 5 5 6 8 8 8 8 9 10 10 11 11 11 12 1 12 2 13 3 13 13 14 15 15 16 16 17 18 19 20 1 A A 1 A 3 3 A Technical Assistance Centre Assistance Centre Maintenance Contract CN...

Страница 24: ...35 40 49 57 2 mbar 13 1 18 4 16 7 23 2 24 C 0 40 C 60 V Hz 230 10 50 60 rpm W V A 2800 3400 300 220 240 2 4 2820 3400 420 220 240 3 A 15 17 A 3 2 3 5 F V 12 5 400 12 5 450 V1 V2 I1 I2 230 V 1 x 15kV 1...

Страница 25: ...MZ LPG EN 676 RS 34 1 MZ RS 44 1 MZ 3010386 RS 34 1 MZ RS 44 1 MZ 3010428 3010429 RS 34 1 MZ RS 44 1 MZ kW 80 390 kW 120 530 kW mm 216 351 216 351 3010423 3010424 3010418 3010419 3010452 3010448 3010...

Страница 26: ...C C H 1 1 4 M 8 x 25 4 M 8 x 25 1 3 1 1 A mm A B C kg RS 34 1 MZ 1000 500 485 RS 44 1 MZ 1000 500 485 B mm A D E F 1 H I L O N V M RS 34 1 MZ 442 422 508 216 351 140 305 138 780 84 177 1 1 2 RS 44 1...

Страница 27: ...5 A 20 C 1013 mbar 0m 9 B EN 676 B 350 Mcal h 50 cm 1 5 m CE B CE B mbar mbar A D8589 B D497 Mcal h kW m...

Страница 28: ...5 9 9 4 8 3 2 350 11 3 76 7 47 8 22 9 11 2 5 4 3 4 375 12 4 86 7 53 7 25 4 12 7 5 9 3 8 390 13 1 57 4 27 0 13 5 6 3 4 0 kW 1 2 MB 407 S5 Rp 3 4 MB 410 S5 Rp 1 1 4 MB 412 S2 Rp 1 1 4 MB 415 S2 Rp 1 1 2...

Страница 29: ...1 1 4 MB ZR 415 S2 Rp 1 1 2 MB ZR 420 S2 Rp 2 100 0 2 2 9 2 1 150 1 6 5 6 2 8 200 3 0 9 0 4 5 3 2 250 4 9 13 2 6 5 3 3 300 6 9 18 0 8 7 4 3 3 2 350 8 9 22 9 11 2 5 4 3 4 400 10 8 28 1 14 0 6 5 4 1 450...

Страница 30: ...B B C L mm 9 RS 34 1 MZ RS 44 1 MZ 216 216 351 351 6 7 9 8 7 8 C C D C 3 2 1 3 100 mm 4 C 5 C 4 1 E 2 E D 2 E 1 E 4 6 Nm mm A B C RS 34 1 MZ RS 44 1 MZ 160 160 224 224 M8 M8 B C D455 D E D3844 D3835...

Страница 31: ...9 A A B 1 A 2 A 3 A RS 44 1 MZ 300kW B 300 kW 4 0 mbar B A C C 4 A 5 A 4 A 5 A 4 D 3 D 5 D 100mm 8 C D 3 2 1 A B N D7565 D8458 D D7566 C D8577 N...

Страница 32: ...000824 3970554 3970230 MB DLE 410 S20 1 3010123 3000824 3970258 MB DLE 410 S52 1 1 4 3010123 3000824 3970144 3970231 MB DLE 412 S20 1 1 4 3010123 3970180 3970232 MB DLE 415 S20 1 1 2 3010123 3970181 3...

Страница 33: ...11 10 A B C 7 8 VR VS 4 18 A 3 C A C B D3855 D3854 D3841...

Страница 34: ...20 kW 120 kW 120 kW 120 kW ts ts 3 1 3 450 kW ts 3 150 kW 24 A 4 10 ts 3 Vg Sm3 Qa Sm3 h n 10 ts G 20 9 45 kWh Sm3 150 kW 15 87 Sm3 h 10 1 5 6 C 11 6 7 VR2 2 A 1 A A D593 Vg 3600 Qa x n x ts Vg 3600 1...

Страница 35: ...13 2 A A CO 100 ppm A A 3 B 5mbar 1mbar C 5 A 4 23 A 100 A A C 4 4 A B RMG 10 D3843 A D3855 D3951...

Страница 36: ...14 A TL 3 0 s 2 s 43 s VS VR VR1 VR1 A VR A B 45 s 53 s VR VR2 C D A TL F G B 3 TL 49 LED 1 A B n 0 D3024 16 D3025 16...

Страница 37: ...15 TL TS...

Страница 38: ...16 LED 10 3 1 3 1 3 2 3 17 3 1 3 LED 17 170V 1 3 3 LED 1 3 3 3 LED LED LED 10...

Страница 39: ...17 2 1 2 3 4 8 D 5 6 7 8 9 10 11 12 13 3 14 15 16 17 18 19 3 20 21 4 22 23 7 24 25 8 D 26 5 A 27 28 29 30 31 10 32 33 34 35 36 37 38 39 40 41 42 43 44 9 45 8 D 46 47...

Страница 40: ...18 LED 3 LED 3 RMG PC 3002719 2 1 0 4 2 0 8 6 2 8 LED 3 3 10...

Страница 41: ...19 EN 60 335 1 RS 34 44 1 MZ 1 TL 7 2 6 3 TR 4 5 2 6 6A 6A RS 34 44 1 MZ 24 TL 24 D11833...

Страница 42: ...nces 4 Electrical panel layout INDEX Electrical wiring is the responsibility of the installation engineer 3 Functional layout 2 Indication of references Sheet no 1 A1 Co ordinates RS 34 1 MZ RS 44 1 M...

Страница 43: ...21 RS 34 1 MZ...

Страница 44: ...22 RS 44 1 MZ...

Страница 45: ...23 RS 34 44 1 MZ...

Страница 46: ...gas pressure switch PGMin Low gas pressure switch Q2 Single phase knife switch RS Remote reset button TA Ignition transformer TL Limit thermostat pressure switch TS Safety thermostat pressure switch...

Страница 47: ......

Страница 48: ...I 37045 Legnago VR Tel 39 0442 630111 http www riello it http www rielloburners com Manufacturing site Riello Heating Equipment Shanghai CO LTD No 388 Jinbai Road Jinshan Industrial Zone 201506 Shang...

Отзывы: