6. Function
The delivery cart is designed for in-house transportation and distribution of food.
Heated well(s), insulated, electrically heated (wet heating), seamlessly welded into the top.
The heated well(s) is/are deep-drawn, suitable for holding 1 GN container of max. size GN 1/1, 200 mm deep,
with heated well installed below, with tubular heating elements, each 765 W/ 230 V.
Each heated well is fitted with a ball drainage cock ½ “, outlet at the bottom.
The number of heated wells 1 – 4 depends on model.
Cart with 1 pushing handle.
Switch panel with 1 thermostat, can be regulated from +30 to +110 °C, per heated well.
Sub-structure: Open tubular frame, with stainless steel shelf and impact protection consisting of 4 corner
bumpers.
2 swivel casters and 2 swivel casters with brake.
7. Commissioning, cleaning, trouble-shooting, decommissioning
Commissioning
for the first time:
•
Clean unit thoroughly (see chapter “Cleaning”)
•
Check that the thermostat is in good working order (if it clicks when turned, it is
intact). Check that the ON/OFF switch and the drainage cock are in good
working order.
•
Close the drainage cock (toggle position horizontal)
•
Fill the heated well(s) with water to a level of 20 mm (approx. 2 litres
respectively); the containers should not float
•
Connect the earthed plug to the earthed socket provided on site
•
Press ON/OFF switch
*UHHQFRQWUROODPSOLJKWVXS 8QLWLVVZLWFKHGRQ
•
Heat up unit (when empty) at the maximum temperature approx. 2 times for 30
minutes.
Operation
•
Hang in the Gastronorm containers from the top
•
Use the knob on the thermostat to set the required temperature for each heated
well
•
After a longer operational period, check the level of water in the heated well (20
mm) and if necessary refill.
Switches/display
Cleaning
•
Activate brakes on the casters
•
Disconnect mains supply plug
•
Open ball drainage cock (toggle position vertical) and empty water into a bucket
provided on site
•
Clean and rinse the well
•
Close the ball drainage cock again
•
If necessary, pre-treat heavily soiled areas
•
Clean the outside of the unit with a damp cloth
•
Allow cart to completely dry off
Warning!
Wipe the switch panel with a damp cloth. No damp may be allowed to penetrate the
switch panel. Dry the plug off after cleaning.
Close / open the
drainage cock
Toggle position vertical: Drainage cock open.
Toggle position horizontal: Drainage cock closed.
Warning! Only open the drainage cock to empty the water.
Decommissioning
•
Press ON/OFF switch
&RQWUROODPSZLOOH[WLQJXLVK 8QLWLVVZLWFKHGRII
•
Disconnect the mains plug and insert into blind socket to prevent damage to the
spiral cable.
•
Empty water into a bucket provided on site by opening the drainage cock.
Warning! Allow water to cool down before emptying, otherwise there is a danger
of scalding from the hot water.
•
Close the drainage cock
Spare parts
Please refer to the Rieber-Online Store at
http://shop.rieber.de
for spare parts.
Spare parts can also be ordered in our service department.
Miscellaneous
Circuit diagrams and a declaration of conformity can be ordered if required.
ON/OFF switch
Ball drainage cock
1 thermostat with
knob per well,
stepless
Blind socket