Repairs

The hub is the only replaceable item in this brake.

General

After proper installation, no further adjustment should be 
required for the life of the unit.

Full rated torque of a new AAB brake may not develop 
until the mating surfaces have been burnished or 

run-in.

Power supply

The voltage to be applied is determined by rating shown 
on the nameplate. Resistance and other coil data for 
various voltages are tabulated on appropriate Engineering 
Data Sheets. This data can be secured by contacting the 
factory.

Troubleshooting for AAB Brakes

Overheating, coil burned out or loss of torque

1. Check ambient temperature. It is above 40° C? Consult 

factory for assistance.

2. Check thermal capacity of unit versus actual heat 

dissipation requirements. Consult factory.

3. Check voltage supply as close to coil as feasible. 

Compare to nameplate data, if incorrect apply proper 
voltage.

4. Is coil resistance correct? Consult factory for resistance 

of the specific coil.

Caution:

 To avoid damage to power supply, hipot testing 

should not exceed 1500 volts for one second. Brake coil 
leads must be connected together.

5. Stop time on brake normally should not exceed one 

second. If excessive, recheck torque rating versus load 
characteristics.

6. Check for oil/grease on friction elements. If this is 

found, replacement of entire brake may be required.

7. On pressure spring, check for broken, missing or 

substituted springs not of our design.

8. Failure to release after unit has performed satisfactorily 

for a period indicates wear has occurred. Replacement 
of the brake is required.

Fuse in DC power supply blows

1. Never put in a higher rating fuse or replace with a

slo-blow type.

2. Check resistance of coil, if shorted, replacement of 

brake is required. If not shorted, obtain coil resistance 
from factory and compare to your reading.

3. If cause was not found in Step 2 above, check rectifier 

bridge by removing all loads and replacing fuse. If 
fuse blows when AC is applied to rectifier, bridge is 
shorted. Replace bridge if feasible or discard control 
and replace.

Size

Hub 

Position 

(inch)

Operating 

Range    

Air Gap 

(inches)

Maximum Allowed 

Misalignment (inches)

X

X

1

Parallel

Angular

2.8

.954 .050 .003 to .015

.005

.005

*Size 2.8 can be pressure plate mounted using the long hub.