Testing and verification
The machine manufacturer or the installer of the UCC MMI-2 is responsible for ensuring that the following testing and verification is
performed to the appropriate standard:
Verification that the electrical equipment is in compliance with the technical documentation
Continuity testing of the protective bonding circuit
Insulation resistance tests
Functional tests, particularly those related to safety and safeguarding
NOTE:
It is strongly recommended that any measuring equipment is regularly checked for accuracy. An initial ‘pass off' test should
be performed prior to normal use.
NOTE:
It is recommended that metrology tests should be performed after any update.
WARNING:
The system installer should intentionally cause a scale fault (for example: by placing a piece of paper between the
readhead and the scale) to check that a scale error is reported during all service and maintenance operations.
UCC MMI-2 installation guide
www.renishaw.com
Issued 08 2020
26