Upon receipt of the HE4XINV, inspect the unit for obvious external damage. If damage is
observed, take digital pictures and report the damage to your RenewAire rep. Note the damage
on the carrier’s Bill of Lading. Depending on expected transport and storage conditions, the unit
may have only the duct openings covered, it may be stretch-wrapped or it may be crated. Do
not unwrap the unit at this time. The unit will normally be moved to its final location while still
wrapped and attached to its pallet.
The preferred method of hoisting the HE4XINV from the carrier truck is by using a construction
forklift.
Once the unit is unwrapped, prevent dirt and debris from entering the cabinet by covering any
duct openings that do not have attached dampers. Keep the duct openings covered until it’s
time to connect ductwork.
SHIPPING/RECEIVING
3.4 HANDLING AND STORAGE
Units that must be stored prior to installation should be left on their pallets and protected from
weather and physical damage. Units must be placed on a level surface to prevent wracking of
the pallet and the HE4XINV. All access doors must be secured with all available hardware (door
latches and securing bolts) and all openings into the cabinet must be sealed to prevent entry of
dust, dirt and debris.
4.0 UNIT PLACEMENT
4.1 BEFORE YOU BEGIN
Units that must be stored prior to installation should be left on their pallets and protected from
weather and physical damage. Units must be placed on a level surface to prevent wracking of
the pallet and the HE4XINV. All access doors must be secured with all available hardware (door
latches and securing bolts) and all openings into the cabinet must be sealed to prevent entry of
dust, dirt and debris.
The HE4XINV is designed for installation in a sheltered location, out of the weather. The
preferred mounting location is to place the unit on a concrete floor.