Check that the stop valves
and valve caps are tight after
carrying out any work on the
refrigerant circuit. If necessary,
use appropriate sealant
products.
NOTE
NOTE
The switch-on delay means
that the compressor only
switches on several minutes
later.
Final tasks
■
Use the remote control to set
the target temperature to the
desired value.
■
Re-fit all the dismantled parts.
■
Instruct the operator on how to
use the equipment.
9. Check the correct function
of the condensation pipe by
pouring distilled water into the
condensation tray.
A bottle with a spout is
recommended for pouring the
water into the condensation
tray.
10.Switch the indoor unit to
cooling mode.
11.Check the correct function
and settings of all regulation,
control and safety devices
during the test run.
12.Check the control system in the
indoor unit using the functions
described in the manual.
timer, temperature settings and
all mode settings in the chapter
"Operation".
Unit dimensions
All values in mm
790
275
200
RM 226 IT / RM 235 IT / RM 326 IT 2,6 / RM 326 IT 3,5 / RM 335 IT / RM 426 IT / RM 435 IT
930
275
200
RM 252 IT
1035
320
220
RM 268 IT
13.Check the overheating,
outdoor, indoor, outlet and
vaporisation temperatures and
record the measured values in
the commissioning report.
14.Remove the pressure gauge.
Check that seals have been
fitted in the sealing caps.