Inspection Prior to Initial Operation
Each product must be inspected prior to initial
operation by a competent person to ensure that the
structure is safe and that it has not been damaged
by incorrect assembly, transport or storage.
Inspection Before Starting Work
Before starting work, the product assembly and all
load-bearing components should be checked for
visual defects. This includes checking the integrity of
all profiles for denting, making sure there is no wear
or elongation on the bolt holes and ensuring that
the trolley moves freely along the beam.
Temperature Range
This product can be operated in ambient dry
temperatures between
-10°F
to 131°F (–23° to
+55°C). Consult your supplier in case of extreme
working conditions.
Notes for Correct Operation
We recommend the use of load-sensing or
overload protection devices on all lifts
The risk assessment and method statement must
take into account any factors that might apply
additional loading to the product during lifting
operations
Suitable, appropriately rated winches and
connection plates must be used for all
applications
Take care when transporting and storing the
product to avoid damage
Assemble only as instructed (ensure all bolts are
present and fitted correctly as per instructions)
We recommend that appropriate PPE is worn
when using the equipment
The product should be set up at a safe distance
from the hazard or lift area, before moving the
structure into place
The beam must be horizontal prior to any lift
and a-frames vertical and parallel to each other
Do not use the product if the trolley does
not run freely along the beam. (for certain
applications, such as when the product is being
used as a restraint point, the trolleys can be
locked into position)
Attach the hoist to the lifting point on the trolley
only, making sure it is attached in a way that
does not expose the user to danger by the
hoist, chain or load
Do not allow the load to swing
When lifting, keep the load low to the ground
Only raise and lower loads when castor brakes
are engaged
To ensure stability of the structure, the
operating span of the beam (C) must be equal
to or greater than the distance between the
castors on the A-Frame (G)
The supporting ground/structure where
the product is to be used must be stable
and capable of withstanding the maximum
expected load applied during use
To avoid side pull, lowering and lifting should
only be carried out when the load chain forms
a straight and vertical line between the load
and lifting attachment point on the trolley. If a
vertical line is not possible you must ensure that
the load is within the footprint of the Gantry
A-frames (refer to figure A).
A
PORTA
GANTRY
1100-6600