5. FIRST START-UP AND COMMISSIONING
Commissioning must be carried out by a service provider with a valid authorization
issued by REGULUS spol. s r.o.
Basic steps before the first start-up:
□ Before the first start up (or after a shutdown of more than 1 day), leave the unit with the
power on for several hours to allow the oil in the compressor to warm up sufficiently.
□ Check that the electrical installation is carried out in accordance with the applicable
regulations and with the label on the unit (check in particular the size of the supply
cable, values of the circuit breaker, residual current device and correct earthing).
□ Check the mains voltage at the installation site.
□ Check that the power cable is not damaged, not located close to a heat source, and
that the terminals on the wiring are properly tightened.
□ Check the correct wiring of electrical components (circulation pumps, valves,
temperature sensors, etc.).
□ Check that the heating system is filled with water, properly air bled and pressurized
(1.5-2.5 bar).
□ Check that the heating system has been properly flushed and filled with clean and
treated heating water that meets the requirements of this manual.
□ Check connections for leaks.
□ Check piping insulation.
□ Check that the shut-off valves of the hydraulic circuits are open and that the water flow
through the unit is not blocked.
□ Check that the inlet and outlet pipes of the unit have not been interchanged.
□ Check that a Magnet Filterball is installed on the return pipe to the heat pump.
□ Check that the fans rotate freely.
□ Make sure that the unit has unrestricted air access.
□ Check that all protective covers are fitted and secured.
Actions following switching on:
□ Switch on the heat pump through the controller and set all necessary parameters of
the control system.
□ When the system heats up, carry out a pressure and heating test. These activities
should be recorded in a heating test and leak test report.
□ Inform the user about the controller control and user menu.
□ Inform the user about the location of switches, circuit breakers and their functions.
□ Inform the user about other safety features and indicators (safety valves, pressure
gauges, analogue thermometers, etc.) and their functions.
□ Check the availability of all documentation of the installed devices.
□ The service provider shall fill in the Heat Pump Commissioning Protocol and the heat
pump owner shall sign it.