10. Remove the six nuts and bolts and bolts that are used to secure the Clean
Edge Frame to the unit. Discard the Clean Edge Frame and hardware.
Remove six nuts and bolts
11. DETERMINE THE THICKNESS OF THE FINISHING MATERIAL. Maximum
of 32mm on both the Clean Edge Frame and Faceplate.
Maximum 32mm
finish material
12. When using the Faceplate Option, the firebox needs to be pulled forward
out of the Zero Shell to the predetermined thickness of the finish material. Posi
-
tion the firebox forward out of the Zero Shell to the predetermined thickness
of the finish material. It is very helpful to use scrap piece of non-combustible
board and tile as a gauge. Ensure unit is centered and in correct position as
this will dictate the location of the spigot, framing and finishing. When using the
clean edge frame, the unit does not require to be pulled out of the zero shell.
Non-Combustible Board
Tile
Finish material sits
behind return flange
of firebox when using
Faceplate
INSTALLATION INSTRUCTIONS
UNIT PREPARATION/FRAMING/CLEAN EDGE AND FACEPLATE WALL FINISHING
13. You are now ready to install the flueing. Loosen the 4 screws on the top of
the unit that secure the adjustable flue plate. Set the plate so the unit spigot
is centered. This is not required when using clean edge frame. Only required
to do when using faceplate option.
Below is the view of the top of the unit prior to installation of the flue. The
packaging material has been removed.
Please refer to Flue requirements on page 12. Install your flue system.
14. After flueing has been installed, complete the install of your optional kits
such as fan and/or outside air kit
Unit without Clean Edge Frame and pulled forward from Zero Shell