installation
GAS PIPE
PRESSURE TESTING
The appliance must be isolated from the gas supply
piping system by closing its individual manual shut-
off valve during any pressure testing of the gas
supply piping system at test pressures equal to or
less than 1/2 psig. (3.45 kPa). Disconnect piping
from valve at pressures over 1/2 psig.
The manifold pressure is controlled by a regulator
built into the gas control, and should be checked
at the pressure test point.
NOTE:
To properly check gas pressure, both
inlet and manifold pressures should be
checked using the valve pressure ports
on the valve.
1)
Make sure the valve is in the "OFF" position.
2)
Loosen the "IN" and/or "OUT" pressure tap(s),
turning counterclockwise with a 1/8" wide flat
screwdriver.
3)
Attach manometer to "IN" and/or "OUT"
pressure tap(s) using a 5/16" ID hose.
4)
Light the pilot and turn the valve to "ON" position.
5)
The pressure check should be carried out with
the unit burning and the setting should be within
the limits specified on the safety label.
6)
When finished reading manometer, turn off the
gas valve, disconnect the hose and tighten the
screw (clockwise) with a 1/8" flat screwdriver.
Note: Screw should be snug, but do not
over tighten.
SIT 829 VALVE DESCRIPTION
1)
Gas on/off knob
2)
Electronically Operated Hi/Lo
3)
Pilot Adjustment
4)
Thermocouple Connection -
option
5)
Outlet Pressure Tap
6)
Inlet Pressure Tap
7)
Pilot Outlet
8)
Main Gas Outlet
9)
Alternative TC Connection Point
REMOTE RECEIVER INSTALLATION
1) Install the heat shield to the receiver with two screws.
2) Attach to the floor of the unit with a velcro pad. Locate the
receiver at the far right hand side of unit as shown below.
3) See Remote Control installation instructions for information on
coding the handheld transmitter to the receiver
Install the supplied battery into the DC Sparker Box
by opening the battery compartment.
NOTE:
The battery in the DC Sparker Box will
need to be replaced annually.
DC SPARK IGNITER BATTERY
INSTALLATION
GAS INSERT
AERATION SYSTEM
The air shutter can be adjusted by moving the
adjusting wire up or down. The wire is accessed
through the bottom louver opening. Open the air
shutter for a blue flame or close for a yellower
flame. The burner aeration is factory set but may
need adjusting due to either the local gas supply
or altitude.
Minimum Air Shutter Opening:
5/16"
Natural Gas
7/16" Propane
CAUTION: Carbon will be produced if air
shutter is closed too much.
Note: Any damage due to carboning resulting
from improperly setting the aeration
controls is NOT covered under warranty.
Note: Aeration Adjustment should only be
performed by an authorized Regency
Installer at the time of installation.
Содержание Energy E33-LP10
Страница 6: ...6 E33 10 FPI Direct Vent Gas Insert 6 dimensions UNIT DIMENSIONS OVERSIZE BACKINGPLATE WITH SPACER ...
Страница 41: ...E33 10 FPI Direct Vent Gas Insert 41 41 notes ...
Страница 46: ......
Страница 47: ......