Ellipse
INSTALLATION GUIDELINES
70-00159-01-09
Proprietary Redline Communications © 2015
Page 28 of 52
April 29, 2015
3.8
Power Source
The installer must provide a compatible power source for the Ellipse system.
The DC
supply connections are located on the front panel of the PoE unit. This is a keyed Buchanan
796864-5 (or equiv.) connector (removable screw-type sector controller block). Dual isolated
floating power supply inputs are provided to accommodate deployments with backup power (e.g.,
A + B battery banks). All power inputs include overvoltage and reverse polarity protection.
Figure 16: Site Survey: Power Wiring
Isolation
The installer must provide pluggable sector controller blocks in the cabinet to isolate the
PoE for installation and servicing.
Surge Suppression
Surge suppression must be provided if the power source is external from the cabinet
(e.g., built-in to sector controller blocks).
: System installation must include dedicated outdoor rated surge protection
for the power cable ingress into the shelter or cabinet.
Power Requirments
The Ellipse system requires up to 17 W of power. The supply cable may be 12 to 22
AWG.
Table 11: Site Survey: Power Requirements
Power
< 17 W
Wire Gauge
12-22 AWG
Cable Supports
It is important to provide strain relief, drip loops and protection against vibration and
abrasion caused by the wind, sand etc. The installer must provide suitable cable
supports for the power cable, spaced at a recommended maximum of 450 -610 mm (~18
- 24 in).