2.0 FIRST INSTALLATION, REMOVING THE MACHINE FROM THE
PALLET
The machine is standing vertically on the pallet. To remove the pallet and lay the machine
horizontally on the ground, proceed as follows (see Fig. 6):
1. Fasten a cable to the lifting point (2).
* Make sure that the cable/crane/lift can lift at least
SS 1200
500 kg (1100 lbs)
SS 1600
600 kg (1322 lbs)
SS 2100
700 kg (1540 lbs)
SS 2400
850 kg (1870 lbs)
2. Raise the machine, including the pallet, 50 mm (2”) from the ground.
3. Remove the pallet by sliding it over the lower 3-point pins
*
Do not crawl under the machine!!
4. Slowly lower the machine until it is standing on the ground.
5. Attach the machine to a tractor.
*
Use the correct tractor. See the specifications.
6. Set the tractor’s stabiliser to 100 mm lateral movement.
7. Drive to the area that is to be tilled.
8. While driving carefully lower the machine into the ground.
9. Switch off the tractor and lock the tractor/Speedseed combination to prevent it
from driving/sliding away.
10. Turn the top rod to adjust the machine angle to 90 degrees.