REC Installation Manual - REC Alpha Panels - IEC 61215 /61730
Rev 13 - 11.22
290 mm
730 mm
410 mm
300 mm
200 mm
0
90 mm
0
300 mm
200 mm
0
300 mm
200 mm
0
300 mm
200 mm
0
520 mm
290 mm
730 mm
410 mm
0
90 mm
520 mm
570 mm
570 mm
CAUTION
The center point of each clamp and the minimum grip length must be fully located in the same clamping zones to be rated to that load (fig. 6).
If the panel is secured in zones with different load values, it is rated to the lowest load value only.
Rail positioning
Rail positioning
Fig. 6: Clamping of REC Alpha Pure-R Series panels with rails parallel to short side of the panel
Legend
Clearance Gap
Clamping zone
20-40 mm
40-60 mm
>60 mm
Test Load
(Design Load)
Test Load
(Design Load)
Test Load
(Design Load)
90 - 290 mm
X
+2400 Pa / -2400 Pa *
(+1600 Pa / -1600 Pa)
+2400 Pa / -2400 Pa
(+1600 Pa / -1600 Pa)
290 - 410 mm
+1800 Pa / -1800 Pa *
(+1200 Pa / -1200 Pa)
+4200 Pa / -2400 Pa
(+2800 Pa / -1600 Pa)
+5400 Pa / -2400 Pa
(+3600 Pa / -1600 Pa)
410 - 520 mm
+1800 Pa / -1800 Pa *
(+1200 Pa / -1200 Pa)
+6200 Pa / -3000 Pa
(+4133 Pa / -2000 Pa)
+7000 Pa / -3000 Pa
(+4666 Pa / -2000 Pa)
520 - 570 mm
+1200 Pa / -1200 Pa *
(+800 Pa / -800 Pa)
+3000 Pa / -2400 Pa
(+2000 Pa / -1600 Pa)
+5400 Pa / -2400 Pa
(+3600 Pa / -1600 Pa)
570 - 730 mm
+2400 Pa / -2400 Pa
(+1600 Pa / -1600 Pa)
+2400 Pa / -2400 Pa
(+1600 Pa / -1600 Pa)
+2400 Pa / -2400 Pa
(+1600 Pa / -1600 Pa)
0 - 200 mm
X
+800 Pa / -800 Pa *
(+533 Pa / -533 Pa)
+800 Pa / -800 Pa *
(+533 Pa / -533 Pa)
200 - 300 mm
X
+800 Pa / -800 Pa *
(+533 Pa / -533 Pa)
+1600 Pa / -1600 Pa *
(+1066 Pa / -1066 Pa)
Installations with a clearance gap between the uppermost part of the roof and lowest part of the panel (i.e., frame) with a clearance
gap of <20 mm are not permitted.
Once a module is secured in each of the 4 zones (fig. 2), additional clamps, i.e., ≥5, may be freely located on panel frame without
affecting the warranty. Loads marked with a
*
were not certified as part of IEC 61215/61730 testing; these have been evaluated by
REC’s internal testing process.
Lo
ng
S
id
e
M
ou
nt
in
g
Sh
or
t S
id
e
M
ou
nt
in
g
Rail position
Rail position
INSTALLATION OF REC ALPHA PURE-R SERIES PANELS
MOUNTING WITH CONTINOUS RAILS PARALLEL TO SHORT SIDE OF THE PANEL
A continous rail (or other support structure) spans the complete underside of the panel.
Legend
Clearance Gap
Clamping zone
20-40 mm
40-60 mm
>60 mm
Test Load
(Design Load)
Test Load
(Design Load)
Test Load
(Design Load)
90 - 730 mm
+1200 Pa / -1200 Pa *
(+800 Pa / -800 Pa)
+1600 Pa / -1600 Pa *
(+1066 Pa / -1066 Pa)
+2400 Pa / -2400 Pa
(+1600 Pa / -1600 Pa)
0 - 200 mm
X
+1200 Pa / -1200 Pa *
(+800 Pa / -800 Pa)
+1600 Pa / -1600 Pa *
(+1066 Pa / -1066 Pa)
200 - 300 mm
X
+800 Pa / -800 Pa *
(+533 Pa / -533 Pa)
+2400 Pa / -2400 Pa
(+1600 Pa / -1600 Pa)
Installations with a clearance gap between the uppermost part of the roof and lowest part of the panel (i.e., frame) with a clearance
gap of <20 mm are not permitted.
Once a module is secured in each of the 4 zones (fig. 2), additional clamps, i.e., ≥5, may be freely located on panel frame without
affecting the warranty. Loads marked with a
*
were not certified as part of IEC 61215/61730 testing; these have been evaluated by
REC’s internal testing process.