FUTERA II START UP CHECK LIST
The following items must be fi eld verifi ed as complete
prior to the scheduling of factory authorized start up.
1. All electrical is installed and checked: ...........................................................
Yes
No
2. All water connections are made: ....................................................................
Yes
No
3. System is fl ooded and pressure tested: .........................................................
Yes
No
4. All pumps (primary or secondary) are running: ..............................................
Yes
No
5. Flow switches installed and adjusted: ............................................................
Yes
No
6. Drain valve installed on outlet prior to isolation (boiler only): .........................
Yes
No
7. T/P gauge installed on outlet prior to isolation (boiler only): ..........................
Yes
No
8. Low water cut off installed and wired: ............................................................
Yes
No
9. Lead/lag/external controls installed and tested: .............................................
Yes
No
10. All gas connections are complete: .................................................................
Yes
No
11. Gas pressure verifi ed between 5" and 14" W.C. .............................................
Yes
No
12. Gas lines purged and tested for leaks: ...........................................................
Yes
No
13. All stacks/vents connected per spec: .............................................................
Yes
No
14. Air inlet duct work and related items installed: ...............................................
Yes
No
15. All boiler related equipment operational: ........................................................
Yes
No
16.
......................
Yes
No
17.
......................
Yes
No
18.
......................
Yes
No
19.
......................
Yes
No
20.
......................
Yes
No