13.) Balance all batteries individually to within one tenth of a volt (.1 V) using the incoming
solar, making sure that the inverter is charging all batteries at an equal rate.
Disconnect Commissioning
14.) Turn off all batteries and the Sol-Ark. Remove the cover from the disconnect.
15.) With all disconnects, breakers, and equipment off, turn on the incoming power to the
disconnect. This may be a generator or the grid, test individually if both.
16.) With the disconnect set to “OFF” use a voltmeter to check
the incoming voltage on the
line side of the disconnect. Check both phase to ground and phase to phase voltage to
ensure the incoming voltage is balanced.
17.) After voltages are verified from both the grid and gen inputs at the disconnect, turn the
power back off to the disconnect. Replace the cover to the disconnect.
18.) Turn the power on to the disconnect. After power is on, throw the disconnect switch to
allow power to the Sol-Ark.
19.) Flip the “Grid” and “Gen” disconnects on the
Sol-Ark
to “ON”. The
Sol-Ark should
recognize the power and turn on.
20.) Verify voltage readings on the Sol-Ark screen coming from the grid and gen.
21.) With the battery disconnect off, turn the batteries on individually.
22.) Turn the battery disconnect on and verify that the grid and/or gen input is charging
the batteries.
IMPORTANT! Ensure that neutral and ground are bonded together at exactly ONE location
in the entire electrical system. This will be in the disconnect on the side of the RaVolt
enclosure.
Load Center Commissioning
23.) Remove the cover of the load center.
24.) Using a voltmeter, measure the voltage of the load side. Measure both phase to ground
and phase to phase voltages to verify that the voltages are balanced.