12
Manual No. 016-3001-015 Rev. C
231
Troubleshooting the Viper Pro System
Job Issues
Issue
Possible Cause
Solution
Section numbers
are gray
• Section switches are
turned off
• Turn section and master switch on.
• Section control enabled
but machine not moving
• Move the machine out of the applied zone.
• CAN is disconnected
section on page 236 section.
Section number
does not turn green
when turned on
• The section is not set up
properly
• Check the section setup from the Setup menu.
• Nodes not completely
programmed
• Check node calibration and ensure all calibration is completed.
• The section is
disconnected
• Check the connection and wiring to the section.
Section control
system will not turn
on
• Section switches are in
the 'Off' position
• Section switches must be in the 'ACCU' position.
INC/DEC function
switch does not
work
• INC/DEC not enabled for
appropriate product(s)
• Assign INC/DEC switch function to the appropriate product(s).
• Product application is
turned off
• Switch product application to either auto or manual mode.
Dates and time are
incorrect
• No GPS
• Make sure that the GPS receiver is operating properly and that
there is a green 'thumbs-up' icon displayed in the GPS section of
the main screen.
• No GPS RMC or ZDA
• Check the GPS receiver to make sure the RMC or ZDA string is
selected.
• Incorrect time zone
selected
• Verify the time zone selected in the
Menu
/
Setup
/
Local
/
Time
Zone
section.
Product applied in
zero rate zones
• Wrong valve type on
vehicle
• Must use either a Fast Close or PWM Close valve (not available
for ground drive air carts).
• Incorrect valve setting
• Check valve or PWM setting.
Содержание OmniSeed Viper Pro
Страница 1: ...Viper Pro Software Version 3 10 OmniSeed Calibration Operation Manual ...
Страница 10: ...Table of Contents viii OmniSeed Viper Pro Calibration Operation Manual ...
Страница 98: ...Chapter 4 86 OmniSeed Viper Pro Installation Operation Manual ...
Страница 150: ...Chapter 6 138 OmniSeed Viper Pro Installation Operation Manual ...
Страница 222: ...Chapter 10 210 OmniSeed Viper Pro Installation Operation Manual ...
Страница 240: ...Chapter 11 228 OmniSeed Viper Pro Installation Operation Manual ...
Страница 250: ...Appendix A 238 OmniSeed Viper Pro Installation Operation Manual FIGURE 1 OmniSeed System Diagram 3 Bin D N 054 5010 003 ...
Страница 251: ...Manual No 016 3001 015 Rev C 239 FIGURE 2 OmniSeed System Diagram 3 Bin D N 054 3001 026 ...
Страница 255: ...Manual No 016 3001 015 Rev C 243 FIGURE 6 Seed Blockage Sensor Cabling More than 60 Sensors D N 054 5002 002 ...
Страница 256: ...Appendix A 244 OmniSeed Viper Pro Installation Operation Manual ...
Страница 284: ...Appendix D 272 OmniSeed Viper Pro Installation Operation Manual ...
Страница 292: ...Appendix G 280 OmniSeed Viper Pro Installation Operation Manual ...
Страница 300: ...Appendix H 288 OmniSeed Viper Pro Installation Operation Manual ...
Страница 304: ...Index 292 OmniSeed Viper Pro Calibration Operation Manual ...
Страница 307: ......