5.6 Tips for using

Do not exceed 10 starting/hour. For more frequent starting, install a soft-start device.

Air can be discharged to the atmosphere through a discharge silencer or it can be piped 
else-where. Pump performance decreases if the pipelines are too small or too long.

6. Maintenance and spare parts

6.1 Maintenance

 All maintenance operations must be carried out with the pump idle, disconnected form 
the elec-trical supply, with the pump cold, vented to atmospheric pressure.
Check the oil level through the suitable oil sight glasses (2) periodically. If needed, top it up.

Change the oil every 5000 (Rotant VF805)/10000 (Rotant VF 315)  hours of operation, 
draining the exhausted oil through the discharge ports (3). Use a oil ISO VG 150. 

When changing the oil also check the coupling elastic element, replace it if required.

Used oil must be disposed of according to local regulations.

If there is an external inlet filter, keep it cleaned to allow full pump performance.

6.2 Spare parts

When ordering spare parts, always state the pump model, serial number, year of produc-
tion, electric motor characteristics (manufacturer’s name, model, kW, V, Hz), position 
reference on the spare parts list, description and quantity needed.

7. Lubricants

Synthetic oil recommended for generic use

Use the synthetic oil for compressors.

Ambient temperature

Grade

PVR oil

5 - 40°C

ISO 150

Rotant VF 315

5 - 40°C

ISO 150

Rotant VF 805

Содержание DRY 100

Страница 1: ...DRY 100 DRY 250 DRY 300 Claw vacuum pumps Operating and maintenance instructions EN TRANSLATION Publication Number LI 2078 05 April 2021...

Страница 2: ...operation page 7 5 1 Location page 7 5 2 Electric connection page 7 5 3 Connection to the machine page 8 5 4 Discharge air pipe line installation page 8 5 5 Commissioning page 8 5 6 Tips for use page...

Страница 3: ...es place The suggestions given to the staff engaged in the installation and servicing assumes that the personnel is expert and prepared in facing any problem of servicing both mechanical and electrica...

Страница 4: ...nnectedtothelowershaftbymeansofacoupling 2 2 Expected use ThepumpsoftheDRYserieshavebeendesignedtohandleairandsmallquantityofwater vapour They are suitable for the evacuation of closed systems or for...

Страница 5: ...th the pump idle disconnected from the electrical supply with the pump cold vented to atmospheric pressure Prevent unexpected start up e g block the power switch with a personal lock ELECTRIC SAFETY S...

Страница 6: ...eck that the packing is intact or if is shows signs of damages occurred during transportation If there is no damage proceed to the unpacking and check further the machine In case damages are found inf...

Страница 7: ...patibility emissionstandardandimmunityforindustrial environments Check the main voltage and frequency in use to correspond to the data stamped on the motor name plate The electric motor must be protec...

Страница 8: ...pipes with the same diameter as the tank discharge port with a maximum length of 15 m For longer pipes increase pipe diameter Pipe weights must not rest on the pump In the final length use flexible p...

Страница 9: ...Change the oil every 5000 Rotant VF805 10000 Rotant VF 315 hours of operation draining the exhausted oil through the discharge ports 3 Use a oil ISO VG 150 When changing the oil also check the couplin...

Страница 10: ...th the pump and advise the risks involved in handling if any Drain the lubricant from the pump prior to shipping the pump back 10 Disposal Meaning of the WEEE logo found in labels The following symbol...

Страница 11: ...PVR Srl HEADQUARTERS Via Santa Vecchia 107 23868 Valmadrera LC Italy T 39 0341 1918 51 F 39 0341 1918 599 info pvr it www pvr it LOCAL UNIT Via IV Novembre 104F 23868 Valmadrera LC Italy...