![PVI Industries 100LX 125 A-PVIF Скачать руководство пользователя страница 41](http://html1.mh-extra.com/html/pvi-industries/100lx-125-a-pvif/100lx-125-a-pvif_installation-and-maintenance-manual_1628757041.webp)
41
PV500-44U 06/12
18
RECOMMENDED MAINTENANCE SCHEDULE
1. Annual
Maintenance
a. Check all joints and pipe connections for tightness, corrosion or deterioration.
b. Check the electronic-ignition system for quick ignition and a proper flame signal.
c. Check all safety controls including thermostats for proper operation.
d. Check safety shut-off valves for operation and tightness.
e. Test flame failure detection system.
f.
Test high limit and operating temperature controls.
g. Conduct a combustion test.
h. Perform leakage test on pilot and main gas valves.
i.
Test air switch in functionality.
2. Semi-Annually
a. Recalibrate all indicating and recording gauges.
b. Check flame failure detection system components.
c. Check firing rate control.
d. Check piping and wiring of all interlocks and shutoff valves.
e. Inspect burner components.
f. Check
igniter.
g. Test high and low gas pressure interlocks.
h. If equipped, check air filter and replace if required.
3. Monthly
Maintenance
a. Test low-water cutoff device and alarm (if equipped).
b. Check flue, vent, stack, or outlet dampers.
c. Check flame signal strength.
d. Check flame failure detection system.
e. Check firing rate control.
f.
Listen to and visually check the pilot and main fuel valves.
4.
Daily Maintenance
a. Check gauges, monitors, and indicators.
b. Check instrument and equipment settings.
5. As
Required
a. Check drip leg and gas strainers.
b. Test flame failure detection system.
c. Test temperature and pressure relief valves in accordance with ASME Boiler and Pressure Vessel
Code Sections VI & VII.
d. Tank flush and cleanout.
Содержание 100LX 125 A-PVIF
Страница 8: ...8 PV500 44U 06 12 250 SERIES ...
Страница 9: ...9 PV500 44U 06 12 300 SERIES ...
Страница 12: ...12 PV500 44U 06 12 SINGLE WATER PIPING SINGLE STORAGE WATER HEATER WITH SUPPLEMENTAL STORAGE TANK ...
Страница 34: ...34 PV500 44U 06 12 16 REPLACEMENT PARTS REPLACEMENT PARTS ...
Страница 35: ...35 PV500 44U 06 12 16 1 Control Panel ...
Страница 37: ...37 PV500 44U 06 12 16 3 Burner Assembly Optional components may or may not be shown ...
Страница 42: ...42 PV500 44U 06 12 PVI INDUSTRIES LLC 3209 Galvez Ave Fort Worth Texas 76111 Phone 1 800 433 5654 www pvi com ...