INSTALLATION INSTRUCTIONS

 

 

Tools Required

Drill 
0# Phillips screwdriver 
1/8” Blade screwdriver 
2mm Blade screwdriver 
Ratchet with sockets 
 

Wire Required

Communication cable between Node panels: Serial Data cable equivalent to Carol C0842A or  
Belden 9842 (120-ohm impedance). CAT Ethernet cable cannot be used.  No Substitutions. 
 
Communication cable for Touchscreen:  Cat 6 (Size based on job) No Substitutions. 

 

 

 

 

 

Installation Procedure 

System consists of  a Master Node panel and one or more Secondary Node panels, dependent on 
the size of the job, and one touchscreen supplied by Performance Sports Systems.   

Determine location for Master Node, all nodes should be securely mounted in a location 
that is easily accessible for maintenance and operation of the Manual Control Override. 

Once the relay box has been properly mounted, wiring of the system can be accomplished. 

Refer to System Wiring Configuration drawing (Page 5) from Performance Sports 

Systems, Model TSC 1500XL. 

 

 

 

 

 

 

 

 

 

 

Содержание TSC 1500XL

Страница 1: ...L Installation Instructions Please read all instructions before attempting installation or operation of these units SAVE THESE INSTRUCTIONS FOR FUTURE USE PUBLICATION NO 8 5 1 7 5 1 2 3 0 R e v A A p...

Страница 2: ...TSC 1500XL 1 Contents Section Page No Introduction 2 Cautions and Warnings 3 Installation 5...

Страница 3: ...tor can easily reprogram each of the passwords to fit their individual security requirements Further the administrator can change the passwords as frequently as necessary TSC 1500XL was designed with...

Страница 4: ...TSC 1500XL 3...

Страница 5: ...sed on job No Substitutions Installation Procedure System consists of a Master Node panel and one or more Secondary Node panels dependent on the size of the job and one touchscreen supplied by Perform...

Страница 6: ...ly for the length of run to meet the electrical service requirements 1 Connect the power wires to the Node panel as follows see Figure 1 Incoming hot to Black terminal block on the left side of the po...

Страница 7: ...ely for the length of run minimum recommended size as follows 12 AWG for up to 90 feet of run 10 AWG for 90 feet to 140 feet of run 8 AWG for 140 feet to 240 feet of run 6 AWG for 240 feet to 380 feet...

Страница 8: ...onnection on both ends The Master Node connection will connect on an open spot on the Ethernet Switch See figure 3 The Touch Screen connection will connect to the Ethernet port labeled Ethernet Figure...

Страница 9: ...wires Route Serial Data cable away from any high voltage lines when connecting to secondary node panels 1 Connect the Serial Data cable to the Master PLC as shown in Figure 5 Use the chart for correct...

Страница 10: ...ection at Secondary Node panels Figure 6 Figure 7 Note Follow installation below for connecting the RJ 45 connector to Serial Data cable this guide is also included with RJ 45 connector Ethernet cable...

Страница 11: ...cording to these instructions Failure to do this can result in an inoperative system sluggish response or inability to reliably control the system components NOTE Do not run communications cable throu...

Страница 12: ...nstallation of conduit and wire all open holes must be plugged by electrician Wiring Practices All AC wiring should be routed away from DC Communication and Control wiring and should never intersect o...

Страница 13: ...Performance Sports Systems 9200 E 146th Street Noblesville IN 46060 800 848 8034 www perfsports com...

Отзывы: