16
Air X Owner’s Manual
User Power
Red Lead
Disconnect
Battery
Green Lead
Switch
Earth Ground
Stop
Turbine Ground
Amp
Meter
Black Lead
Turbine Negative
Earth Ground
Battery Bank
Box
Lightning Arrestor
Turbine Positive
Junction Box
Center Junction
Up-Tower
Tower
Chassis
Ground
AIR BREEZE
Wind Turbine
Generator
Fuse or
Breaker
Fig. 10. Single Turbine Installation with Up-Tower Junction Box
Fig. 10
represents a system with an Up Tower Junction
Box. The junction box may be installed close to the top of
the tower to ease installing a Lightning Arrestor. Typically
installing the box will require drilling holes in the tower to
install the box – be careful not to compromise the tower
strength.
Air X
TIP:
batteries wired in series and
Battery bank illustrated
is configured as four 6-volt
bank configuration and system
voltage are site specific.
=