background image

 
Troubleshooting and bench check procedures: 

 
 

1.   Connect up test wiring as shown below and insulate the gray and 
white leads coming from the SE900. 
 
2.   Input 120vac into the SE900 (the light should be off). 
 
3.   Connect the red wire thru a 1000 ohm, half watt resistor to terminal 

AC1 on the SE900.  (the light should come on) 
 
4.   Disconnect the red wire from terminal AC1 of the SE900  (the light 
should go off). 
 
5.   Check the SCR and Diode for isolation from the mounting housing. 
 
6.   If all of the above tests could be performed, the unit is good.  If any 
of the tests could not be performed, the unit is defective. 
 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

resistor,

1000  ohm  @

1/2  watt

120  vac

input

fuse,  1  amp

15  to  100
watt  120
vac  light
bulb

R E D

AC1

AC2

SE900

F+ 

Отзывы: