Initial Setup and Commissioning
1. Refer to your voltage regulator’s instruction manual for initial setup and commissioning
of the voltage regulator.
2. If using the Automatic-Flash configuration, follow the initial setup and commissioning
instructions of your voltage regulator as shown in the voltage regulator’s instruction
manual.
3. If using the Battery-Flash configuration, follow the initial setup and commissioning
instructions of your voltage regulator as shown in the voltage regulator’s instruction
manual, except energize or turn on the switch to the AFM500X when you plan to
energize the generator during setup.
4. Observe the buildup operation and verify there is no excessive voltage overshoot and
that the voltage regulator is operating properly.
5. If using the Battery-Flash configuration, always remember to open the switch or relay
contact connected to the AFM500X when shutting the generator down. This will prevent
a drained battery when the generator is stored.
6. When you are satisfied with the buildup performance of the generator, the setup and
commissioning is complete.