8.0
Commissioning the Boiler
16
8.3
Completion
1. Flush the system again and treat it in
accordance with BS7593, Section 5.1 of these
instructions and the flushing agent and inhibitor
manufacturer’s instructions.
2. Carefully read and complete all sections of the
“Benchmark” Installation, Commissioning and
Service Record Log Book that are relevant to the
appliance and installation. The details of the Log
Book will be required in the event of any
warranty work. The Log Book must be handed to
the user for safe keeping and each subsequent
regular service visit recorded.
3. Instruct the user in the operation of the boiler
controls and the function and resetting of the
various safety devices
4. Hand over the User’s Operating, Installation
and Servicing Instructions and the Log Book,
giving advice on the necessity of regular
servicing.
5. Refit the outercase front and top panels
(Fig. 21).
Securing
Screws
Top Panel
Front Panel
Fig. 21
Magnets