7.0 Installation
14
7.2
Making the Electrical Connection
1. Undo the two securing screws from the rear
of the top panel. Remove the panel (Fig. 13).
2. Swivel the two retaining plates through 90°.
Lift the control box slightly and allow it to hinge
forwards (Figs. 14 & 15). Undo the two retaining
screws and remove the cover panel.
3. The input wiring to the boiler and the pump
feed from the boiler should be routed through
the grommet/clamps in the control box rear
panel (Fig. 16).
4. Remove the clamps from the panel and slit
the grommets with a suitable knife or blade.
5. Determine the length of the wiring and secure
in the clamps.
6. Connect live, neutral, earth, and switched live
to L, N, & SL of the terminal strip. The pump
live, neutral and earth should be connected to
PL, PN & of the terminal strip (Fig. 17).
1.4
Securing
Screws
Top Panel
Front Panel
Cover Panel
Fig. 13
Fig. 15
Fig. 16
L
N
L
H
T
SWL
View inside control box with cover
panel removed.
Terminal Strip
Earth Point
Burner Ignition
Control
Connection
Cable Clamps
Grommet
Temperature
Control
Thermostat
Fig. 14
L
N
L
H
T
SWL
Fig. 17
Terminal Strip
Magnets
Safety
Thermostat