7.
MOUNTING INSTRUCTION
LIFTING ThE RAIL
3
1
4
2
1. VSR profile
2. Support bracket
3. Horizontal support, C-profile
4. Support trolley with safety hook.
Lift the rail with a minimum of lifting points every 10 m/33`.
Attach the safety hook of the support trolley to the support
brackets according to the picture below.
C/C SPRINGS/SAFETY wIRES
1. VSR profile
2. Centering spring
3. Safety wires
Drill a 6.5 mm/0,25” hole, 800 mm/2,6` from the support leg, as shown in the picture below.
Screw the M6 eyebolts with M6 nuts into the hole.
Fix the centering spring between the hook on the horizontal support and the eyebolt.
Drill a 8.5 mm/0,33” hole, 100 mm/4” from the support leg as shown in the picture below.
Screw the safety eyebolts to the rail with 2 pcs of M8x25.
Mount the safety wires with a wirelock into the safety eyebolts and around the support pipe, as
shown below, or around the ceiling beams.
800 mm
2,6`
100 mm
4”
3
2
1