PIKA Harbor Flex SB10p Скачать руководство пользователя страница 1

M00017-02

Operations Manual

Pika Harbor Smart Battery

Harbor Flex / Harbor Plus

Part of the Pika Energy Island™

Содержание Harbor Flex SB10p

Страница 1: ...M00017 02 Operations Manual Pika Harbor Smart Battery Harbor Flex Harbor Plus Part of the Pika Energy Island ...

Страница 2: ...Harbor Smart Battery Serial Number RCP Number ...

Страница 3: ...of quality If you find any inconsistencies or errors in this document please notify us at sales pika energy com Check the resources tab at www pika energy com for the latest specifications and manuals 11 21 17 Pika Energy Inc All rights reserved All information in this document is subject to copyright and other intellectual property rights of Pika Energy Inc This material may not be modified repro...

Страница 4: ...tdown 8 Battery Modules 8 Section 3 Operation and Controls 10 Communication 10 System Operational Modes 10 Battery State of Charge SOC Setpoints 11 User Interface 13 Section 4 Powering the Nanogrid Without Utility Power 15 Islanding 15 Power Search 15 Blackstart 16 Service and Maintenance Instructions 18 Annual Inspection and Maintenance 18 Service 19 End of Life 19 Section 6 Technical Reference 2...

Страница 5: ...3 Harbor Smart Battery Operation Manual M00017 02 Table of Contents ...

Страница 6: ...le components of the Pika Energy Island system from Pika Energy This Operation Manual includes full details on the use operation and maintenance of Harbor The companion document to this Operation Manual is the Harbor Installation Manual Please reference the Installation Manual for complete information on installing wiring and commissioning the Harbor smart battery Symbols used in this Manual WARNI...

Страница 7: ...s Islanding Inverters to form the Pika Energy Island system for grid tie solar plus storage All Pika Energy products use the REbus 380VDC nanogrid to connect energy sources storage loads and the grid The REbus nanogrid automates the flow of power to enable plug and play setup and operation of Pika Energy equipment For more information about REbus visit pika energy com In the diagram below a REbus ...

Страница 8: ...r make or model to your Harbor Smart Battery including any other lithium ion battery or any other type of battery WARNING Use ONLY Panasonic DCB 105 lithium ion battery modules DO NOT CONNECT ANY OTHER BATTERY MODULES DOING SO WILL VOID THE WARRANTY AND MAY DAMAGE THE HARBOR SMART BATTERY Refer to the manufacturer s documentation for information on the correct handling storage and use of your batt...

Страница 9: ... Code NEC ANSI NFPA 70 WARNING Electrical installation in Canada shall be done in accordance with all local electrical codes and or the Canadian Electrical Code WARNING Connecting the Pika Energy Island to the electric utility grid must only be done after receiving prior approval from the utility company and installation completed only by qualified personnel licensed electrician s WARNING This equ...

Страница 10: ... of AC grid power Upon entering a Safety Shutdown a shutdown signal will be transmitted to all devices connected to REbus In Safety Shutdown the Islanding Inverter will disconnect from the grid stop sourcing power to REbus and immediately disable all sources on REbus by sending a global shutdown signal All PV Link optimizers will disconnect their output The Safety Shutdown LED will be illuminated ...

Страница 11: ...CT EMERGENCY SERVICES Inform the dispatcher that there are lithium ion batteries in the building Keep a carbon dioxide or dry chemical fire extinguisher near the battery location for use in emergency by trained personnel only Emergency personnel Refer to the manufacturer s instructions and or Safety Data Sheet for complete information on fire fighting ...

Страница 12: ...control via a SunSpec interface Contact Pika Energy for more information on how to interact with Harbor via SunSpec System Operational Modes The Pika Energy Island system has several operational modes available for various installation configurations markets and applications The Operational Mode is selected through the front control panel of the Islanding Inverter The Islanding Inverter prioritize...

Страница 13: ...ilable This will prevent the system from operating in Self Supply until the battery SOC increases If the grid goes out and the system begins Islanding then the battery will supply backup power normally Default value is 50 If you lower this setpoint you will have more battery capacity available for Self Supply and other non backup uses but your guarnteed Islanding reserve will be smaller in the eve...

Страница 14: ...7 02 Battery State of Charge SOC Setpoints keeping the lights on for a longer time but the Power Search reserve will be smaller If you raise this setpoint the system may shut down sooner during an outage but the Power Search reserve will be larger ...

Страница 15: ...s switch controls a set of internal relays which disconnect the battery string from the battery monitoring system BMS electronics Always initiate a Safety Shutdown from the inverter and turn this switch to Off before servicing any part of the Pika Energy Island to prevent Harbor from energizing the REbus Nanogrid This switch may be locked in the Off position If the system will be powered down and ...

Страница 16: ...n you may lock this switch in the Off position LED LED state Interpretation strobe interval Green 3 sec solid at powerup Enabled operation starting Red 3 sec solid at powerup Disabled Red green alternating Initializing connecting battery and REbus system energizing Green solid Enabled charging Green strobe Enabled standby 3 secs Green flashing Enabled discharging Yellow solid Waiting Red strobe Di...

Страница 17: ...ing Inverter will shut down and the building will lose power While it is sleeping the Harbor battery spends most of its time in a very low power state Every 30 minutes Harbor will perform a Power Search During a Power Search Harbor wakes up energizes the REbus Nanogrid to 380VDC and scans for potential sources of power If there is another source of power available such as PV Link then Harbor will ...

Страница 18: ...However if Harbor is disabled or the front panel switch is Off at the time at the utility grid loses power then the REbus nanogrid will de energize and all REbus devices will power down In this state no REbus devices can source or sink power and the Islanding Inverter cannot provide backup power to the AC Critical Loads until the user manually performs a Blackstart To Blackstart turn the switch to...

Страница 19: ...hted red turn the switch back to the OFF position 4 Perform steps 1 3 three times in total 5 Turn the switch ON for a fourth time Harbor is now enabled If the battery has sufficient charge then the front panel LED will light green to indicate that the battery is enabled and the system will Blackstart and resume normal operation To avoid the need for a Blackstart always keep Harbor enabled connecte...

Страница 20: ...r or under the Harbor Ensure that the bottom intake vent and front exhaust vent are clear at all times Filter Remove and inspect the bottom intake filter Clean the filter with a vacuum cleaner compressed air or water To remove the filter push the filter straight towards the wall to compress the retention springs Then pull the front edge down and slide the filter out To re install the filter revers...

Страница 21: ... WARNING DISCONNECT ALL POWER SOURCES BEFORE SERVICING Disconnect Harbor from DC sources and turn the front panel Battery Disconnect switch to OFF before opening the cover Verify that voltage at the REbus terminals is at a safe level before proceeding If you are experiencing a problem with your Harbor smart battery contact a qualified installer or technician for appropriate service Qualified perso...

Страница 22: ...az A60Q40 2 40A 600Vdc Main battery string fuses alternate Ferraz A60Q35 2 35A 600V Main battery string fuses alternate Cooper Bussmann Eaton KTK 40 40A 600Vdc Blackstart Battery Fuse Littelfuse 0235005 HXP 5A 125Vac Technical Support Information Support department hours 9AM to 5PM Eastern Standard Time Zone Monday Friday excluding holidays Phone 207 887 9105 Email support pika energy com ...

Страница 23: ...uous 6 7 4 5 kW Power Surge 10 6 7 kW Battery Mod ules 6 4 Lithium ion NMC Panasonic DCB 105 Weight 411 186 311 141 lb kg DC Voltage per module 52 Vdc DC Current Continuous 24 A Round Trip Efficiency 90 Recommend ed Operating Temperature 13 30 55 86 C F Acceptable Operating Tem perature 0 50 32 122 C F Dimensions 68 375 1737 x 22 558 x 9 87 251 in mm Weight Battery Module 55 25 lb kg Communica tio...

Страница 24: ...t Battery Operation Manual M00017 02 Service Section 13 Notes Use the following pages to record notes about your system or to document phone calls with our service department available M F 9AM 5PM ET at 207 887 9105 ...

Страница 25: ...23 Harbor Smart Battery Operation Manual M00017 02 Section 13 Notes ...

Страница 26: ...24 Harbor Smart Battery Operation Manual M00017 02 Service ...

Страница 27: ...www pika energy com 35 Bradley Drive 1 Westbrook Maine 04092 ...