18
3
Heating Cable Installation
Raychem-IM-H58067-IceStopRoofGutterDeIcingCOM-EN 18/01
and follow the attachment recommendations in
“Attachment Methods‚” page 29. Additional heat-
ing cable may be needed for gutters, downspouts,
and valleys and is covered in Section 3.
Figure 6: layout on a standing seam room
• Run the heating cable up the seam until it is 12"
(30 cm) past the exterior wall and into a heated
area, Figure 4 on page 16.
• Run the heating cable up one side of the seam,
loop it over to the other side, and return it to the
bottom of the gutter. Continue along the bottom
of the gutter to the third seam and repeat the
process (Figure 5). If the seams are more than 24"
(60 cm) apart, trace every seam.