probability has a wire touching 

the stator shell at some point 

and the stator will have to 

 

be replaced.

5.  Winding resistance test. if 

motor shows a satisfactory 

ground check then the winding 

resistance must be checked. 

Use ohmmeter with scale 

pointer set on r X 1 scale. on 

this scale, meter reads directly 

on ohms. always check the 

meter with leads together 

 

as described above, under 

ground check, before making  

a reading on the winding.

 

connect  one  meter  lead  to        

the terminal with the brown 

 

 

wire connected underneath 

the terminal board. connect 

the  other  lead  to  the  terminal      

housing with the blue wire. 

meter should read 1.2 to 1.4 

ohms; this is the resistance of 

the main winding for a 115 

volt    stator. This reading for 

a 230 volt stator should be 4.8 

to 5.9 ohms. Now connect one 

meter lead to the brown wire 

terminal and the other meter 

lead to the red wire beneath 

the terminal board. The meter 

should read 3.8 to 5.4 ohms 

for a 110 volt stator. For a 230 

volt stator this reading should 

be 16 to 21 ohms. This is the 

resistance of the start winding. 

Now connect one meter lead to 

the red wire and one to the blue 

wire. The meter reading should 

be the sum of the other two 

readings or 5.0 to 6.8 ohms 

for a 115 volt stator or 20.8 to 

26.9 ohms for a 230 volt stator. 

if the readings obtained do not 

agree with those given, the stator is 

defective and must be replaced.

6.  replacing seal. if water is 

found  in  motor,  seal  must           

be replaced. remove bottom 

casting (5). Place screwdriver 

in shaft slot and tap impeller 

(6) lightly with hammer to 

unscrew. Use cloth on impeller 

to prevent cutting hand. Tap on 

end of shaft with a plastic or 

rubber hammer. This will push 

seal (8,9) from shaft. clean 

case thoroughly; all sand and 

dirt must be removed. remove  

stationary ceramic seat of 

seal from housing. Push new 

ceramic seat into housing. Use 

Parker o-ring lube on rubber 

ring. replace rotor in housing. 

Use care in putting shaft 

through ceramic seat to be 

sure it is not chipped. inspect 

seal after shaft is in place. if 

seal has been chipped it must 

be replaced. do not replace 

 

rotating part of seal until 

 

the balance of the pump 

 

is assembled.

7.  Bearings. When the pump 

rotor has been removed, check 

bearings before replacing. if 

bearings are rusted or rough 

when turned, they must be 

replaced. Pull bearings with 

a bearing puller. if puller 

cannot be replaced over lower  

bearing, remove the outer race 

by cracking in a vise. after 

outer race is cracked, it can be 

removed and the balls can be 

removed. This will allow inner 

race to be pulled.

  When replacing bearings push 

only on inner race. if a press is 

not available, bearings can be 

tapped on, using a sleeve that 

bears only on the inner race.

  Never pound on the outer race 

or bearing will be ruined.

8.  reassembly of stator and 

housing.  replace stator (20) 

with terminal block turned 

toward switch pocket as shown 

by drawing. replace plate and 

bolts (2). Be sure ears on plate 

are in place inside of shell of 

stator.

  replace cord (21) with push on 

terminals in place on terminal 

block. Bend tabs of push on   

connectors down so that they 

cannot touch plate or housing. 

Place wire in straight up 

 

position so that housing (24) 

can be replaced over wire. 

Be sure  bearing load springs 

are in place in housing before  

replacing housing. Hold springs 

in place in housing with o-ring 

lube, or other heavy grease. Be 

sure rubber ring (3) is in place 

on case when lowering housing 

into place. Tap down on top of    

housing with plastic or rubber 

hammer to seat over bearing. 

replace screws (10) and 

 

tighten evenly from one side 

to the other until housing is  

firmly in place. at this point 

turn shaft to be sure rotor 

 

is free. if rotor binds, it 

 

indicates screws are not 

 

tightened evenly.

  Push rubber seal ring (26) 

around cord and replace cord 

nut (25). Tighten cord nut 

tight. Nut must be tight enough 

so that cord cannot be pulled 

up. Put cord into switch cap 

and secure with rubber ring 

and nut. replace switch as 

described earlier.

  Now replace rotating part of 

seal (8). Use tapered installing 

sleeve furnished with seal to 

push over shaft threads. Screw 

impeller (6) onto shaft. Hold 

shaft with screwdriver in slot 

to tighten on impeller. replace   

bottom casting (5).

5

Содержание Hydromatic SP50

Страница 1: ...to the owner of the pumping equip ment or to the responsible party who maintains the system OWNER S MANUAL Submersible Sewage Ejector Pumps 2014 Pentair Ltd All Rights Reserved W 03 232 03 27 14 293 WRIGHT STREET DELAVAN WI 53115 WWW HYDROMATIC COM PH 888 957 8677 ...

Страница 2: ...PA 70 2001 Failure to heed above cautions could result in injury or death General Information Pump Warning Note Some city regulations do not allow installing a pump with plastic pipe Check local regulations 5 In applications where the pump may sit idle for months at a time it is recommended that the pump s be cycled every month to ensure the pumping system is working properly when needed 6 Hydroma...

Страница 3: ...3 Pump Installation ...

Страница 4: ...ur oil in container preferably glass so that oil can be observed If oil is clear it will indicate motor is not burned and there has been no water leaking into the motor If oil is cloudy or black it will indicate water in the motor or a burned stator After draining oil remove bolts 10 and remove cord nut 25 from motor cord 21 Remove rubber seal ring from around cord Turn cord and lift up until seal...

Страница 5: ...l after shaft is in place If seal has been chipped it must be replaced Do not replace rotating part of seal until the balance of the pump is assembled 7 Bearings When the pump rotor has been removed check bearings before replacing If bearings are rusted or rough when turned they must be replaced Pull bearings with a bearing puller If puller cannot be replaced over lower bearing remove the outer ra...

Страница 6: ...dy for check run before air testing and filling with oil Plug cord 21 into power receptacle and push up on switch chamber diaphragm 23 to start motor Motor should start and run smoothly When pressure is released on diaphragm motor should stop Repeat operation 2 to 3 times to be sure operation is satisfactory and not binding 9 Air test To air test unit put air fitting in plug opening 12 and charge ...

Страница 7: ...Cord Nut 1 22 14623 010 1 Power Cord 10 1 22 14623 020 1 Power Cord 20 1 23 139 014 1 Ring Seal 1 1 11584 043 4 Nameplate 1 2 14981 001 1 Plug Pipe 1 4 1 3 56 023 2 Motor Housing Includes Handle 1 4 13594 000 1 Motor 200 V three phase 1 4 13595 000 1 Motor 230 or 460 V three phase 1 4 13596 000 1 Motor 575 V three phase 1 5 77 003 1 O Ring Sq cut 1 6 239 005 1 Bolt 2 7 208 000 2 Flange Discharge 1...

Страница 8: ...ute 1 10 203 010 2 Bottom Plate 1 11 614 010 2 Impeller Automatic Manual 1 12 19109A070 Jam Nut 1 13 83 007 1 Seal Shaft 1 14 83 002 1 Seal Assy Stationary 1 15 19099A029 Screw 1 4 20 6 16 51752 404 7 Switch Pressure Ass y Pg 1 17 30 021 1 Screw 1 18 5502 005 1 Bracket Switch 1 19 101 008 1 Screw 4 20 24709110000 Oil Paraffinic 1 21 75 007 1 Cord Nut 1 22 14623 020 1 Power Cord 20 1 23 139 014 1 R...

Страница 9: ..._____________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ _______...

Страница 10: ..._____________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ _______...

Страница 11: ..._____________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ ____________________________________________________ _______...

Страница 12: ... be accepted if received after the Warranty Period has expired This warranty is not transferable EXCEPTIONS Hydromatic Special Application Pumps Battery Back Up Sump Pumps Filtered Effluent Pumps Grinder Pumps and 2 1 2 Sewage Pumps are warranted for a period of 12 months from date of purchase or 18 months from date of manufacture whichever comes first HYDROMATIC SHALL NOT BE LIABLE FOR ANY CONSEQ...

Отзывы: