Installer manual Fleck 4600 MECH - Maintenance
58 / 92
Ref. MKT-IM-027 / C - 12.11.2019
9.1.3
Regeneration test
9.1.3.1
Valve used for softening
1. Check condition of brine tank and any associated equipment.
2. Check salt level in brine tank.
3. Initiate regeneration test.
ð
Check brine draw during brine draw stage.
ð
Check brine tank refill.
ð
Check operation of safety brine valve, where fitted.
ð
Check for brine draw off levels.
ð
Check for resin loss at the drain during regeneration.
ð
Where fitted, check for satisfactory operation of solenoid, i.e. outlet shut off during
regeneration and/or brine line shut off valve(s).
4. Test and record Total Hardness of outlet water from softener vessel(s).
9.1.3.2
Valve used for filtration
1. Initiate manual regeneration and observe flow to drain.
2. Make sure flow rate correspond to DLFC configuration.
3. Check for media loss at the drain during backwash.
4. Check to see if water runs clear at the end of the backwash cycle.
5. Observe flow fast rinse cycle and measure pressure drop thought the filter system. Pressure
drop after fast rinse should return equal or very close to pressure drop recorded after
system start-up.
6. Where fitted, check for satisfactory operation of solenoid valve(s) i.e. outlet shut off during
regeneration.
Содержание Fleck 4600 MECH
Страница 1: ...FLECK 4600 MECH INSTALLER MANUAL WATER PURIFICATION...
Страница 17: ...Installer manual Fleck 4600 MECH Description Ref MKT IM 027 C 12 11 2019 17 92 3 3 Outline drawing...
Страница 91: ...Installer manual Fleck 4600 MECH Notes Ref MKT IM 027 C 12 11 2019 91 92...
Страница 92: ...www pentairaquaeurope com...