(for installation of GLB in cluster, see User manual at www.
pcelectric.at/de/info/emobility.html
1)
GLB Wallbox without RCCB or RCBO included in the
enclosure must have Residual Current protection and
must be protected with a max 32A fuse in the supply
distribution box.
2)
GLB Wallbox without RCCB Type B fitted or DC fault
protection in the enclosure must in accordance to IEC
60364-7-722 be protected with a Residual Current
Device (RCD) Type B.
3)
3-phase GLB Wallbox equipped with a Residual Current
Circuit Breaker (RCCB) must be protected with a max
32A fuse in the supply distribution box.
4)
1-phase GLB Wallbox fitted with a Residual Current
Breaker with Overcurrent Protection (RCBO) can be
connected in parallel. This group of chargers must be
protected by a backup fuse in the distribution box. The
backup fuse shall not exceed 125A.
GLB Type
Protection type
1-phase
3-phase
No RCBO or RCCB
RCBO
RCCB type A
RCCB type B
DC-fault protection
GLB..-..37..
2) 4)
GLB..-..74..
2) 4)
GLB..-..22..
1) 2)
GLB..-..22..-A
2) 3)
GLB..-..22..-B
3)
GLBDC..-..37..
4)
GLBDC..-..74..
4)
GLBDC..-..11..
1)
GLBDC..-..22..
1)
GLBDC..-..22..-A
3)
1.
Select the appropriate group fuse (1x6A - 3x32A) and
cable area for the electrical installation. Some countries
require earth fault breakers to be installed. Follow local
country regulations and select the appropriate earth fault
equipment for the electrical installation. NOTE! Due to
high currents for a long time in the cable, there is a high
risk of voltage drop if the cable is under-dimensioned
which can damage the electronics in an EV.
2.
Fill in the information in the handover report.
3.
Mount the GLB Wallbox according to the installation
sketch, (figure 1-7)
4.
Install the electrical power supply cable according to local
regulations.
5.
Set dip switch SW1 to same (A) as the main fuse (16-
63A). SW1 is located at the center left hand side of the
main board. See figure 8-11.
6.
Set the dip switch SW2 according to your group fuse
for the GLB Wallbox ( 6-32A). Dip switch 2 is located at
bottom left corner of the main board. See figure 12-13.
7.
Fill in serial number in the handover report. See figure 14,
Serial No / SSID label.
8.
Mount the box cover on the enc front lid, see
figure 14-15.
9.
Turn on the electrical power to the GLB Wallbox.
10. For GLBW… and GLBDCW… models: Connect a mobile
device (PC/Tablet/Mobile) to the GLB Wallbox Wifi
network. You find SSID and password on the rating label.
Type in 172.24.1.1 in your web browser and check
that the GLB webinterface is visible. This action confirms
that the GLB Wallbox communication module is working
properly.
11. Test the charger with a test instrument or test to charge
an electric vehicle to ensure that the charger is working
properly.
12. Doublecheck that the handover report is filled in
completely, sign with name, date and company that the
warranty is valid.