Step 9—Installing Operating Mechanism 

Either a swing handle or a worm gear 

mechanism is (normally) supplied for manual 

switch operation.

 

 

Swing Handle Operator  

To install the swing handle operator: 

With ground strap in place on vertical operating 

pipe, slide handle and handle lock plate over the 

end of the vertical operating pipe. Fasten the lock 

plate at the proper location.  Recommended height 

for the lock plate is 3 ft. 6 in. above ground.   

 

Note:

  

The lower end of the vertical operating pipe 

should extend through the lock plate at least 3 

inches.  It may extend as much as 3 feet or more, 

just so it doesn’t touch the ground or column 

footing.  

 

The lock plate assembly (Fig. 8) consists of two 

castings, mounted on the pipe guide plate, which 

can be easily adjusted in an arc to provide the 

required rotation.  These act as locks for the 

manual operating handle when it is dropped from 

the operating position.  The handle must be raised 

to a horizontal position for operation.  With the 

switch in the fully closed position, set the handle 

clamp so its set screws are 4 inches above the lock 

plate and its vertical centerline is at or near as 

possible to the closed position, see Fig. 8. 

Temporarily fasten the handle to the pipe with the 

set screws.  Operate the switch and move the 

adjustable lock castings until they exert pressure 

against the handle in both the open and closed  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

positions  of the switch. This provides a slight 

torsional wind-up in the operating pipe. Tighten the 

two piercing set screws on the handle clamp until 

holes are punched into the pipe and continue until 

the screws are firmly seated.  

 

 

 

 

 

Fig. 6 MO-10 Motor Operator

 

Fig. 5 Worm Gear Operator  

Содержание TTT7

Страница 1: ...IB TTT7 May 2012 ...

Страница 2: ...ase and Operating Connecting Rods 4 Step 8 Installing Vertical Operating Pipe 4 Step 9 Installing Vertical Operating Pipe and Operation Mechanism 5 Step 10 Arcing Horns or Arc Restrictors 7 Step 11 Installation of Sleet Corona Shields 7 Step 12 Final Checks 7 Maintenance 7 Terminal Connections 7 Renewal Parts 9 Suggested Tools 15 16 Open End Wrench 15 16 Socket 3 4 Open End Wrench 2 3 4 Socket 1 1...

Страница 3: ...ic representative HANDLING Handling of disconnect switches should be done with care Porcelain is fragile and may be damaged due to improper handling Factory drawings should be followed during installation It is recommended that switches be fully assembled and adjusted at ground level before being placed into position This should minimize final adjustments Lifting of switches by insulators contacts...

Страница 4: ...essary to adjust the insulator columns for variation in heights or proper angle use the shims leveling bolts or leveling screws as provided see Fig 1 Step 5 Mounting Current Carrying Parts Rotate the center insulator column to the open position as shown on the drawings The stop at the bottom of the column limits the travel At this time the crank at the bottom of the insulator column will be at an ...

Страница 5: ... three pole switch In fact after all three poles have been adjusted in the open position and then closed you may find that one pole will be high on the right one fairly level and one high on the left This is due to many variables and tolerances plus the free play or clearance in pin connections of all the switches and control parts 6 3 Blade Engagement When Switch is Closed Due to varying friction...

Страница 6: ...ide plate which can be easily adjusted in an arc to provide the required rotation These act as locks for the manual operating handle when it is dropped from the operating position The handle must be raised to a horizontal position for operation With the switch in the fully closed position set the handle clamp so its set screws are 4 inches above the lock plate and its vertical centerline is at or ...

Страница 7: ...6 P a g e ...

Страница 8: ...blades should make central entry into their jaws at approximately the same time 3 In the closed position all blades must be in full contact with jaw contacts and also vertical within the tolerances described previously The stop at each switch base and the stop for the operating bearing should be touching or nearly so The indicator to the worm gear operating mechanism should indicate the switch is ...

Страница 9: ...ntact surfaces of conductors and fittings using a stiff wire brush to remove heavy oxide coatings until the aluminum finish is visible and restored 2 Prepare any bare copper surfaces in the usual manner 3 Coat these now clean contact areas with a liberal amount of corrosion inhibitor such as NO OX ID A Special or no 2 EJC 4 Abrade the contact surface through the corrosion inhibitor using a stiff w...

Страница 10: ...each switch pole The same data is shown on the record engineering drawings The master file at the factory is linked to the serial number on the nameplate Renewal Parts Ordering Information Serial Number Switch Type Part Name Quantity Required Max kV B I L kV Cont Amps Mom Amps Refer your requests for renewal parts to the Factory ...

Отзывы: