background image

7 | 

P a g e

 

 

Swing Handle Operator  

To install the swing handle operator: 

1.

 

With ground strap in place on vertical 

operating pipe, slide handle and handle lock 

plate over the end of the vertical operating 

pipe 

2.

 

Fasten the lock plate at the proper location.  

Recommended height for the lock plate is 3 

ft. 6 in. above ground.   

Note:

  

The lower end of the vertical operating 

pipe should extend through the lock plate at 

least 3 inches.  It may extend as much as 3 feet 

or more, just so it doesn’t touch the ground or 

column footing. 

3.

 

The lock plate assembly (Fig. 9) consists of 

two castings, mounted on the pipe guide 

plate, which can be easily adjusted in an arc 

to provide the required rotation.  These act 

as locks for the manual operating handle 

when it is dropped from the operating 

position.  The handle must be raised to a 

horizontal position for operation. 

4.

 

With the switch in the fully closed position, 

set the handle clamp so its set screws are 4 

inches above the lock plate and its vertical 

centerline is at or near as possible to the 

closed position, see Fig. 8.   

5.

 

Temporarily fasten the handle to the pipe 

with the set screws.   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Worm Gear Mechanism  

1.

 

With ground strap in place on vertical 

operating pipe, slide worm gear mechanism 

over the vertical operating pipe and attach it 

to the structure. 

2.

 

Remove the small position indicators, which 

are attached to the worm gear coupling with 

allen set screws. 

3.

 

Tighten hex head set screws in the coupling 

until the vertical operating pipe is pierced. 

4.

 

If all stops at switch elevation have been set, 

including the offset bearing, then it is safe to 

reinstall the position indicators on the worm 

gear mechanism.  These indicators should 

not quite touch the raised boss on the worm 

gear housing in either the open or closed 

position.  There is a possibility of damage to 

the indicators or the coupling if this is not 

observed 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Motor Operator 

For remote operation, a motor operator is 

supplied and it should be installed per the 

instructions supplied with it.   

 

Step 13—Arcing Horn Installation  

Arcing horns are furnished only when horn 

gap switches are ordered. When arcing 

horns are used, they should be installed and 

Содержание DR7

Страница 1: ...IB DR7 A May 2012 ...

Страница 2: ...tall Interphase Rods and Offset Crank Rod 5 Step 10 Install Vertical Operating Pipe 6 Step 11 Install Pipe Splice and Guide Plate 6 Step 12 Install Operating Mechanism 6 Step 13 Arcing Horn Instillation 7 Step 14 Installation of Corona Rings and Balls 8 Step 15 Final Checks 8 Terminal Connections 8 Maintenance 8 Bearings 9 Renewal Parts 10 Lubrication 10 Suggested Tools 15 16 Open End Wrench 15 16...

Страница 3: ...nd file a claim immediately with the transportation company and notify your Pascor Atlantic representative HANDLING Handling of disconnect switches should be done with care Porcelain is fragile and may be damaged due to improper handling Factory drawings should be followed during installation It is recommended that switches be fully assembled and adjusted at ground level before being placed into p...

Страница 4: ...y contain an additional crank Step 3 Insulator Stack Alignment Lower voltage switches 8 25 thru 72 5kV generally do not require insulator stack alignment Where required the insulator stacks of switches thru 242kV can be aligned using open end shims or leveling screws and or adjusting nuts Fig 1 if supplied optional If using shims place the shims under the insulator supports rotor bearing or spacer...

Страница 5: ... tension nor compression in the rod Adjustment may be made by removing the pin at the attachment point of crack and clevis loosening the locknut screwing the clevis in or out to adjust the length until the proper length is obtained The locknut is then tightened and final assembly of the pin is made to attach clevis and crank After this has been accomplished the closed position stop bolt A Fig 5 is...

Страница 6: ...forms an angle of approximately 45 degrees with an offset link in either switch position closed or open On 5 base circle switches the multi angle crank is installed on the top of the switch crank on 3 base circle switches it is installed on the bottom Step 9 Install Interphase Rods With all blades in the closed position install the interphase rods and offset crank rod as follows a Lengthen the int...

Страница 7: ...on to the offset bearing shaft or on the pole unit rotor bearing in the case of direct connection switches Step 11 Install Pipe Splice and Guide Plate When the length of the vertical operating pipe exceeds 23 feet a pipe splice and a guide plate are furnished and should be installed as shown in Fig 8 The pipe spice and both pieces of pipe are pre drilled to receive the 5 8 diameter pins The guide ...

Страница 8: ...its vertical centerline is at or near as possible to the closed position see Fig 8 5 Temporarily fasten the handle to the pipe with the set screws Worm Gear Mechanism 1 With ground strap in place on vertical operating pipe slide worm gear mechanism over the vertical operating pipe and attach it to the structure 2 Remove the small position indicators which are attached to the worm gear coupling wit...

Страница 9: ...rminal clamp if available to the aluminum switch terminal pad If a non tinned terminal clamp is used apply a liberal amount of electrical joint grease at the joint and all over the pad of the fitting To connect aluminum to aluminum terminals 1 Clean all contact surfaces of conductors and fittings using a stiff wire brush to remove heavy oxide coatings until the aluminum finish is visible and resto...

Страница 10: ...icants are MOBIL 28 grease or NO OX ID A Special MOBIL 28 is an Exxon Mobil Company product NO OX ID is made by SANDCHEM INC 1 ANSI C37 35 American National Standard Guide for the Application Installation Operation and Maintenance of High Voltage Air Disconnecting and Interrupter Switches In general operating linkages require virtually no maintenance However in contaminated atmospheres of where op...

Страница 11: ...mps Refer your requests for renewal parts to the Factory Table 2 Lubrication Guide for Outdoor Switch Components Part Name Type Lubricants Recommended Amount Applied Qty Req d for 6 Three pole Switches Jaw Fingers NO OX ID Grade A Special or Mobil 28 Grease Medium Coat Blade Ends NO OX ID Grade A Special or Mobil 28 Grease Medium Coat 1 Quart Pins On current carrying parts Mobil 28 Grease or DC 4 ...