![Parkeon StradaPAL Скачать руководство пользователя страница 17](http://html1.mh-extra.com/html/parkeon/stradapal/stradapal_installation-manual_3695898017.webp)
7 - Excavation anchoring
StradaPAL – Installation manual
17/43
7.4
Anchoring in an excavation at minimum height
For this installation height (minimum height):
The form may be used but is not indispensable.
The anchoring guard plate is not used.
Fix the anchoring rods to the base box using 8x M16 nuts so that the ends of
the rods are
104 mm
away from the fastening brackets.
- The nuts are to be placed (104 mm away from the end of the anchoring rods)
as instructed for secure installation.
- Mind the positioning direction: the front of the base box must be placed
according to the direction of the terminal to be installed on it.
Put in place the form in the base box (if used).
Front of the base
box
Base
box
104+/
-
1
m
m
Anchoring
rod
D9729
Fastening
bracket
Base
box
Form
D8761