v 1.6 - to be used from 28/09/2017 
 

 

Perform all test runs

 and check the results (See chapter 8, 

pages 93 ff

 install. manual) 

Make  sure  that  all  test  runs  are  done  and  double  check  that  the  results  are  ok!  The  test  runs  are 
required  for  safety  and  warranty  reasons  and  are 

not  optional.

  Perform  the 

Back-Up  operation  test  

(page 94)

 and the 

Reverse current CT test (page 95)

 

Check the test run results! 

Switch  on  the  AC  supply  for  the  Network  Adaptor.  Make  sure  both,  battery  system  and  network 
adaptor  are  running  and  check  the  communications  between  the  network  adaptor  and  the  storage 
battery system. (See chapter 9, 

page 98

Take the 

Setting Manual

 for the network adaptor and follow it step by step.  Make sure the connection 

settings to the server are correct (

page 8, Setting Manual

). Use Mode 2!!! The URL of Utility Server 1 is 

always:          

in.solarcity.panabattery.com  

Please call 

021 025 67893 or 027 349 1950

 to finalize this step while on site. Regardless of the planned 

comms connection, it is worth to bring an alternative solution such as an Ethernet or Wifi bridge.   

Take the 

User Manual

.

  It is most important that you read and understand the user manual before you 

go on site. 

If you have any questions please get in touch with solarcity! The two relevant settings are 

No 

1, No 2 and No 6

.  

1.

 

no  1  Operation  mode 

  Always  set  the  battery  to 

Maximum  self-consumption  mode  (self)

unless specified otherwise. (

page 15

User Manual

2.

 

no 2 Lower discharge limit - 

Set the lower discharge limit to 0%, unless discussed otherwise. A 

higher value keeps a definite reserve for the backup supply, so the battery is never empty when 
backup power is needed. Discuss with the customer and make them aware of the implications 
(less usable power in normal operation) A value of 15% is enough to power a laptop and router 
for 8 hours. (

page 16

User Manual

3.

 

no 6 Stand-alone operation start setting

 - Chang this value to 

CH - 01 for manual start. Explain 

this to the customer! Off-Grid mode should be started and stopped manually. 

 

Explain

  the  lower  discharge  limit  setting  to  the  customer  and  show  how  to 

activate  and  deactivate 

back-up  operation

. Explain that the 

loads

 connected to the back-up supply 

must  not  exceed  2kW

, as 

this is the maximum (the internal RCBO will trip and servicing will be required). Find out what appliances 
the customer would like to run on back-up power in case of emergency and discuss the lower discharge 
limit settings in this context.  

ALWAYS call solarcity to confirm that all user settings have been set correctly and comms are working 
fine. You can reach our engineers until 11pm on 021 0256 7893. If there are any issues and you cannot 
contact us via mobile, you must notify us via email immediately - 

[email protected].

 

Отзывы: