Installation manual 

 

 
 

 

Apex 

In most cases, the apex is supplied in one piece (attention: in some house options, the apex can comprise 
several parts! In this case, these parts will have to be screwed together prior to other actions). Having installed 
the last wall logs, place the apex on the front and back walls and attach them with screws.  

The apexes have indents for the rafters. The rafters also have the corresponding indents, ensuring that the 
roof is placed firmly and in the right place. 

Now place the rafters in the 
corresponding indents in the 
apexes.  

Make sure that the upper wall log, 
apexes and rafters are level. Having 
fitted the rafters, screw them onto 
the apex from above. 

 

 Installation of rafters: 

 

 

ATTENTION

: If the wall logs are not properly pressed on top of one another without gaps, the upper wall log 

may not be on the same level with the apexes. In this case you should tap the wall logs downwards as 
necessary or plane the apex or sidewall log somewhat lower.  

 

Roof 

Before installing the roof boards, make sure that the house is completely level. Use the water-level to 
check all walls. 

ATTENTION

: When placing the roof, use a stable ladder. Do not step on the roof as the structure is 

suitable to sustain only an even load (snow, wind, etc.), and not a point load! 

Begin the installation of the roof boards 

from the front edge of the roof

. Tap the boards lightly and 

attach them from above and below with nails to the rafters and upper wall log.  

ATTENTION

: Do not press the roof boards together too densely and you will avoid moisture-causing 

bulging! Leave an interval of about 1 mm between the boards to allow for swelling. 

 

During the whole process of installing the roof boards, make sure that their crest rafters coincide 
and the eave sides of the boards extend at a uniform distance. Verify this with a rope or the lateral 
eave lath that you may install for verification purposes.  

 

The roof boards must be even with the rafter ends in front and behind. If necessary, saw both last 
roof boards so narrow that they are even with the rafter ends.  

www.simplylogcabins.co.uk

Содержание FRG28-4032

Страница 1: ...ieures sont exclues Si une réclamation avait lieu veuillez respecter le déroulement suivant Il vous faudra présenter à votre commerçant spécialisé ce bulletin de contrôle avec le récépissé de l achat Ce ne sera que moyennant présentation de ces documents qu un traitement rapide et sans problème de votre réclamation sera possible Italiano La casetta che avete acquistato è stata prodotta secondo la ...

Страница 2: ...récépissé Data prova d acquisto Fecha recibo Kvitteringsdato Kasse bons dato Forwarder Pick up Others Door Verzending Zelf afhalen Spedition Selbstabholer Par Transporteur Propres moyens Tramite Spedizioniere Mezzo proprio Entrega Transporte organizado transporte propio Transportør Sendes Hentes Transportør Sendes Hentes Description of complaint Beschrijving van de klacht Schilderung der Beanstand...

Страница 3: ...oduktet Alle rechten en technische wijzigingen voorbehouden Installation manual Montageanleitung Notice de montage Istruzioni per il montaggio Manual de montaje Monteringsanvisning Installatiegids Log cabin FRG28 4032 ZL Art Nr 881392 Blockhaus Maisonnette en poutres Casa di travi Casa de jardin Anneks Tuinhuis Width 400 x Depth 320 cm Breite Tiefe Largeur Profondeur Lunghezza Profondita Ancho Pro...

Страница 4: ...ly review complaints if you submit the control number of the house to the seller The warranty does not cover Peculiarities of wood as a natural material Wooden details already painted processed with a wood preservative Wooden details containing whole branches that do not endanger the stability of the house Colour tone variations caused by wood structure differences that do not influence wood lifet...

Страница 5: ...mpregnation agent and do that namely both inside and outside Otherwise the doors and windows can become twisted After the house assembly is completed we recommend for the conclusive finishing a weather protection paint that will protect wood from moisture and UV radiation When painting use high quality tools and paints follow the paint application manual and manufacturer s safety and usage instruc...

Страница 6: ... sure that there are sufficient air apertures under the house floor for ventilation We recommend the following foundation options Strip or spot foundation Foundation from concrete or pavement slabs Cast concrete bed Prepare the foundation so that the foundation joists are propped up on every side with intervals not exceeding 50 60 cm Consult an expert in this field or have the foundation prepared ...

Страница 7: ... are not included in the supplied kit Installation of foundation joists Walls When installing the walls it is important to remember that The logs are always assembled with their tongue upwards If necessary use the hitting block and hammer Never directly hit the tongue with the hammer Install the walls in accordance with the appended wall plans see Technical specifications First of all place half l...

Страница 8: ...ow To open and close the door fit the separately packaged lock and handle Window installation Continue with the installation of the wall logs until you reach the window height The wall plans see Technical specifications show how many logs go under the window Install the window similarly with the door Just like the door push the window frame with the window into the window aperture onto the lower l...

Страница 9: ...idewall log somewhat lower Roof Before installing the roof boards make sure that the house is completely level Use the water level to check all walls ATTENTION When placing the roof use a stable ladder Do not step on the roof as the structure is suitable to sustain only an even load snow wind etc and not a point load Begin the installation of the roof boards from the front edge of the roof Tap the...

Страница 10: ...t nails at intervals of about 15 cm Make sure that the felt strips overlap by at least 10 cm Having installed the roof cover material attach the wind braces to the roof and the facia boards to the rafters and upper wall logs Installation of wind braces and facia boards Floor Only when the house is built completely you can install the floor boards thus avoiding unnecessary smudging on the floor Pla...

Страница 11: ...ends of the slats Do not turn the screws tightly so wood can further swell or diminish With the house having settled you should adjust the attachments so the wall logs can settle Installation of storm braces General advice Problem Gaps appear between the wall logs Cause Additional details are attached to the house that do not allow wood to swell diminish Solutions If the door window is attached to...

Страница 12: ...w w w s i m p l y l o g c a b i n s c o u k ...

Страница 13: ...w w w s i m p l y l o g c a b i n s c o u k ...

Страница 14: ...w w w s i m p l y l o g c a b i n s c o u k ...

Страница 15: ...w w w s i m p l y l o g c a b i n s c o u k ...

Страница 16: ...w w w s i m p l y l o g c a b i n s c o u k ...

Страница 17: ...w w w s i m p l y l o g c a b i n s c o u k ...

Страница 18: ...w w w s i m p l y l o g c a b i n s c o u k ...

Страница 19: ...w w w s i m p l y l o g c a b i n s c o u k ...

Страница 20: ...w w w s i m p l y l o g c a b i n s c o u k ...

Страница 21: ...w w w s i m p l y l o g c a b i n s c o u k ...

Отзывы: