Mount BG02
●
Place near enough to the equipment being monitored
to ensure voltage and CT lead lengths will fit
●
Place within 30 feet of Packet Power Ethernet Gateway
or other Packet Power monitoring device
●
Use attached mounting tabs for wall mount or
the included chase nipple to install directly onto
equipment
●
Mounting tabs have #0.18 hole
Run CT leads from the BG02 to device being monitored
Connect CTs to the conductors
●
Consult the CT Specification Sheet for correct CT orientation
Connect CT tails to the CT leads coming from the BG02
●
CTs from full-power meters will be labeled L1, L2, L3; ensure they are placed on the proper phase
●
CTs from current-only meters will be labeled CT1, CT2, CT3, ... and are not phase-specific
Run the voltage leads to the voltage source and connect by line and ground
●
If there are multiple voltage sources, the voltage leads will be labeled accordingly
●
Ensure adequate over-current protection is provided
Once power is supplied, the BG02 will automatically begin to transmit data.
© 2019 Packet Power LLC
BG02 QS V1
BG02 Quick Start Guide
SERIOUS OR FATAL HAZARD WARNING:
Ph (877) 560-8770 ext 2
www.packetpower.com
2716 Summer St. NE
Minneapolis, MN 55413
USA
Disconnect power prior to installation and ensure installation is done by a qualified person according to local electrical codes.
Detailed information can be found at packetpower.com/support.