……………………………………………… USER AND MAINTENANCE HANDBOOK L150A
P.Energy
P.Energy
P.Energy
P.Energy
20
-
30
3.7.2
– START UP LAMINATOR
INITIAL REQUIREMENTS (Valid for
all tests)
The operator who works with this machine have to know all instructions of this manual.
All electrical, pneumatic and hydraulic connections have been done as previously described.
The laminator main switch on electric cabinet should be on "0" position.
SAFETY REQUIREMENTS (Valid for
all tests)
The operator has to be in front of operator panel which must be placed outside the opening radius of cover.
A second operator has to support the first one in order to avoid dangerous behaviour.
1. It’s necessary to remove the closing plate on the left side
2. Giving power supply to the electrical cabinet by turning on the main switch in “1” position
3. Check the operator panel start up and verify the home page appears on the touch
4. Turn to release the red "Emergency" pushbutton.
5. Push the blue button "Auxiliary insertion".
6. If some alarms appear on operator panel, select the "ALARMS" page where it’s possible RESET all alarms
7. Choose the "MANUAL COMMANDS” PAGE AND PUSH FOR FEW SECONDS THE VACUUM PUMP BUTTON.
The second operator will be positioned on the left side of the laminator to control the pump rotation direction correspond to direction indicated by a sticker
applied to the pump.
8. If the pump rotation direction is not the same it is necessary to take off immediately the vacuum pump command on touch screen, and cut off the voltage.
After that, it’s necessary to reverse two phase of laminator power cable and test again the rotation of direction.
If the pump rotation direction is right the laminator is ready to work
We recommend testing one to one all the manual commands in order to verify that all features are ok before to start an automatic cycle.