Installation Quick Guide
Switching the zone displays to other side
of the coil panels:
Lay the Metor 6E down. Place a support
under the cross piece so that only the
coil panel bottoms touch the ground
(e.g. the cardboard package the cross
piece came in).
Detach the top piece (1) which is held in
position by four screws.
Detach the zone display cable connector
(2) and the counter cable connector (3)
from the top of the tubes.
DO NOT remove the green and red
cables on top of the panel. DO NOT
switch the positions of the cables.
Gently slide out the zone display and
counter tubes to the direction indicated.
Slide the tubes gently in on the opposite
sides of the coil panel.
Reconnect the cables in corresponding
connectors. Check that connectors lock
in position.
Re-install the top piece and fasten it with
the four screws.
DO NOT over tighten the screws as you
may damage the thread in coil panel.
If you are installing an additional zone
display simple remove counter tube and
replace it with the zone display tube.
NOTICE
After changing the side of the zone display you need to select correct zone display
mode from the user interface to enable the zone display using menu “2.4.1 ZONES”.
Refer to chapter 7.4 for further information.
Do not switch zone displays between panels as it will cause counter malfunction. Zone
displays for panel 1 have blue RX stickers on them and displays for panel 2 have red
TX stickers. Same applies to infrared RX/TX counters.
CAUTION
While assembled three persons are recommended for safe lifting and lowering of the
equipment.
Rapiscan Systems Proprietary Information