BAFFLE INSTALLATION AND BRICK NOTES
1.
Stack the baffle boards (A) on top of the vermiculite boards (B) as shown in figure 3a .
Figure 3a
2.
Put them on the horizontal air duct (C) (see figure 3b). Afterwards, push them towards the bottom
and sides so that they rest on the back of the firebox (D) and on the side air ducts. Install the baffle
support/extension (H) ensuring that it fits between the front risers and hold it in place. Install the
front secondary air tube as show in figure 3c ensuring air holes face forward. Install the cotter pins
as in fig 3.4. Installing the front secondary air tube (E) will stabilize baffle assembly during the next
step.
Figure 3b
Содержание OB02212