Install the parts of the post-combustion
chamber dry. In the event of joints that have
not been closed (depending on the joint
thickness when erecting the red jacket
bricks), the joints must be sealed with
ceramic fibre. However, the parts of the post-
combustion chamber should not be bonded
with each other.
Now install the remaining rows of the GOS. In
the course of this, in places a 6 mm air gap
must be created between the bricks.
Caution: The GOS without nubs must be
placed in the top row.
Joint pattern GOS:
An OPEN joint must be created after the 2
nd
and 4
th
row GOS.