GENERAL INSTRUCTIONS FOR PREFORMA PF-4 / 5
ASSEMBLY AND USE OF PREFABRICATED PRIVATE
STATIONS (LV METERING)
IG-138-FR
version 02
02.10.2007
Page 18 of 28
6. ADDITION INFORMATION
6.1. RE-SUPPLY OF THE LV or MV
Re-supply is done by means of adapted cables passing through the access hatch provided.
The access hatches are captive through use of chain with links.
Use is made of this hatch as follows:
1.
Inside the substation, slightly unscrew the two nuts retaining the vertical plate.
2.
Unscrew the central nut WITHOUT taking it out.
3.
Release the outer plate by passing the retaining nut through the slot provided for this
purpose.
4.
Place the external plate on the ground - a retaining chain is fixed on this plate and keeps
it captive.
5.
Slide the internal plate upwards, in order to pass through the recharge cables which will
be placed in a layer in the hole.
6.
Lower the internal hatch down to the stop on the recharge cables.
7.
Retighten the two screws in order to fasten the plate on the cables.
To bring out the recharge cables, do the operations in the reverse order.
6.2. TAKE-DOWN OF THE SUBSTATION AT END OF LIFE
All the materials forming the substation enclosure are recyclable.
The take-down of the substation at end of life must be done as follows:
1.
Apply all the regulatory provisions in force to proceed withdraw the structure from service.
2.
Clear the perimeter of the substation to access the anchorage systems to do the lifting.
Leave at least 300 mm clearance to place the DEHA anchors.
3.
Place the slings as indicated in this document.
4.
Lift the substation and load it onto the truck.
The substation is made of fibre-reinforced concrete. It can be crushed to be used as road
sub-base. The metal features (steel) can be recycled by the competent bodies.
6.3. SPARE PARTS
For all spare parts or technical information, please contact Ormazabal's Technical-Sales
Department.