GENERAL INSTRUCTIONS FOR PREFORMA PF-4 / 5
ASSEMBLY AND USE OF PREFABRICATED PRIVATE
STATIONS (LV METERING)
IG-138-FR
version 02
02.10.2007
Page 16 of 28
Normal unloading conditions are:
Access to the unloading site by a truck (19 m long x 2.5 m wide x 4.50 m high).
Zone stabilised for unloading (slope < 1%).
Absence of aerial or other objects within a sufficient radius (electricity lines, telephone
lines, trees, pipes, walls, etc.).
For any other delivery conditions, consult Ormazabal's Technical– Sales department.
4.3. CONSTITUENT PARTS
PREFORMA enclosure (PREFORMA-PF-4 / 5 according to order description).
Neutral grounding connection
Re-supply hatch, temporary supply (external).
Fixture frames for MV, TGBT boards, electronic switchgear.
Regulation
notices
Extinguisher
Safety booms and detex.
Glove
box.
Insulating
mat
Fixtures for MV connection: UF/Transf.
Oil recovery pit.
The substation's internal circuits: internal li autonomous safety lighting unit.
According to Order:
MV
Board
Earthing
circuit
Options
Green tariff metering table
Vent shuttering system (on request).
Auxiliary
supply
board.
BAPI (Portable Lighting Box)
MV connections between MV and transformer,
LV connections between transformer and TGBT.
Circuit-breaker on chassis or TGBT.
Condenser
battery.
Lightning
conductor.
On the order, the customer must specify the power, the LV neutral regime, the equipment,
the options and the installation's boundary conditions (harmonics rate; risk of explosion, fire;
reference ambient temperature; oversizing coefficient Possible customer).
WARNING:
For the mounting of the gripping systems, they must face upwards, so the sling hook is
located at the top.